Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 2items · current page 1–2 · Source records, not unique facilities.
Power assets and projects · USA · eia860
Glines Hydroelectric Project
Generation facilities · Unverified
Metric or condition
Source value
Basis, scope and stage
Grid Voltage (kV)
69 kV
Original source column definition · Power plant · Unverified As-of date 2025 Sources EV-4d2192f91a3be001959aa1de
Detailed source fields
Original source field
Published value or condition
Utility ID
2518
Utility Name
U S Bureau of Reclamation
Plant Code
54050
Plant Name
Glines Hydroelectric Project
Street Address
Hwy 101, Elwha River at mi. 12
City
Port Angeles
State
WA
Zip
98362
County
Clallam
Latitude
48.0022
Longitude
-123.6002
NERC Region
WECC
Balancing Authority Code
BPAT
Balancing Authority Name
Bonneville Power Administration
Name of Water Source
Elwha River
Primary Purpose (NAICS Code)
22
Regulatory Status
RE
Sector
1
Sector Name
Electric Utility
FERC Cogeneration Status
N
FERC Small Power Producer Status
N
FERC Exempt Wholesale Generator Status
N
Ash Impoundment?
N
Ash Impoundment Lined?
X
Transmission or Distribution System Owner
PUD No 1 of Clallam County
Transmission or Distribution System Owner ID
3644
Transmission or Distribution System Owner State
WA
Grid Voltage (kV)
69
Energy Storage
N
Coordinate accuracy
source_precision_not_independently_surveyed
source_record_id
2___Plant_Y2025.xlsx#Plant:3625
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 1itemseia860 ↗
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.