Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 2items · current page 1–2 · Source records, not unique facilities.
Power assets and projects · USA · eia860
Twin Falls Hydro
Generation facilities · Unverified
Metric or condition
Source value
Basis, scope and stage
Grid Voltage (kV)
230 kV
Original source column definition · Power plant · Unverified As-of date 2025 Sources EV-b8eeb91973776bf9bc965cc2
Detailed source fields
Original source field
Published value or condition
Utility ID
64078
Utility Name
Central Rivers Power US, LLC
Plant Code
50827
Plant Name
Twin Falls Hydro
Street Address
49032 Southeast 177th Street
City
North Bend
State
WA
Zip
98033
County
King
Latitude
47.444554
Longitude
-121.687812
NERC Region
WECC
Balancing Authority Code
PSEI
Balancing Authority Name
Puget Sound Energy
Name of Water Source
Snoqualmie River
Primary Purpose (NAICS Code)
22
Regulatory Status
NR
Sector
2
Sector Name
IPP Non-CHP
FERC Cogeneration Status
N
FERC Small Power Producer Status
Y
FERC Small Power Producer Docket Number
82-224
FERC Exempt Wholesale Generator Status
N
Ash Impoundment Lined?
X
Transmission or Distribution System Owner
Puget Sound Energy Inc
Transmission or Distribution System Owner ID
15500
Transmission or Distribution System Owner State
WA
Grid Voltage (kV)
230
Energy Storage
N
Coordinate accuracy
source_precision_not_independently_surveyed
source_record_id
2___Plant_Y2025.xlsx#Plant:3458
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 1itemseia860 ↗
Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.