POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 2items · current page 1–2 · Source records, not unique facilities.

Power assets and projects · USA · eia860

Cherokee Dam

Generation facilities · Unverified

Metric or conditionSource valueBasis, scope and stage
Grid Voltage (kV)161 kVOriginal source column definition · Power plant · Unverified
As-of date 2025
Sources EV-bd4f79855924c2280fb5ed12
Detailed source fields
Original source fieldPublished value or condition
Utility ID18642
Utility NameTennessee Valley Authority
Plant Code3397
Plant NameCherokee Dam
Street Address450 POWER HOUSE RD
CityRudledge
StateTN
Zip37861
CountyJefferson
Latitude36.168176
Longitude-83.49768
NERC RegionSERC
Balancing Authority CodeTVA
Balancing Authority NameTennessee Valley Authority
Name of Water SourceHolston River
Primary Purpose (NAICS Code)22
Regulatory StatusRE
Sector1
Sector NameElectric Utility
FERC Cogeneration StatusN
FERC Small Power Producer StatusN
FERC Exempt Wholesale Generator StatusN
Ash Impoundment Lined?X
Transmission or Distribution System OwnerTennessee Valley Authority
Transmission or Distribution System Owner ID18642
Transmission or Distribution System Owner StateTN
Grid Voltage (kV)161
Energy StorageN
Coordinate accuracysource_precision_not_independently_surveyed
source_record_id2___Plant_Y2025.xlsx#Plant:1620

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 2___Plant_Y2025.xlsx#Plant:1620

Sources EV-bd4f79855924c2280fb5ed12
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 dd99ff396e6b5bf130d209b7e45b4e8245a89f7973f3a69322e01b9d6fe53768

Usage terms US government public domain

Source snapshots by date · USA · eia860

Cherokee Dam

Power plant · Unverified

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID18642
Utility NameTennessee Valley Authority
Plant Code3397
Plant NameCherokee Dam
Street Address450 POWER HOUSE RD
CityRudledge
StateTN
Zip37861
CountyJefferson
Latitude36.168176
Longitude-83.49768
NERC RegionSERC
Balancing Authority CodeTVA
Balancing Authority NameTennessee Valley Authority
Name of Water SourceHolston River
Primary Purpose (NAICS Code)22
Regulatory StatusRE
Sector1
Sector NameElectric Utility
FERC Cogeneration StatusN
FERC Small Power Producer StatusN
FERC Exempt Wholesale Generator StatusN
Ash Impoundment Lined?X
Transmission or Distribution System OwnerTennessee Valley Authority
Transmission or Distribution System Owner ID18642
Transmission or Distribution System Owner StateTN
Grid Voltage (kV)161
Energy StorageN
source_record_id2___Plant_Y2025.xlsx#Plant:1620

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 2___Plant_Y2025.xlsx#Plant:1620

Sources EV-bd4f79855924c2280fb5ed12
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 dd99ff396e6b5bf130d209b7e45b4e8245a89f7973f3a69322e01b9d6fe53768

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel