POWER & FACILITY EVIDENCE
Power and Facility Evidence Database Review power assets, contract observations, facility specifications and relationships from public sources.
Global Facilities and Power Map Korea Site and Power Map Korea Data Center Database This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 3items · current page 1–3 · Source records, not unique facilities.
Power assets and projects · USA · eia860m Intercession City / P1 Generator · Operations
Metric or condition Source value Basis, scope and stage Nameplate Capacity (MW) 56.7 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-23ca0495ceeaa40fbbd0b68b Net Summer Capacity (MW) 45 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-23ca0495ceeaa40fbbd0b68b Net Winter Capacity (MW) 60 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-23ca0495ceeaa40fbbd0b68b
Detailed source fields Original source field Published value or condition Entity ID 6455 Entity Name Duke Energy Florida, LLC Plant ID 8049 Plant Name Intercession City Google Map Map Bing Map Map Plant State FL County Osceola Balancing Authority Code FPC Sector Electric Utility Generator ID P1 Nameplate Capacity (MW) 56.7 Net Summer Capacity (MW) 45 Net Winter Capacity (MW) 60 Technology Petroleum Liquids Energy Source Code DFO Prime Mover Code GT Operating Month 5 Operating Year 1974 Status (OP) Operating Latitude 28.262778 Longitude -81.54861 Original text (OP) Operating Coordinate accuracy source_precision_not_independently_surveyed source_record_id Operating:8091
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Operable:8089
Sources EV-ebe46476b34ef779d52ba420 Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 5a75b7a7b74aef5827fa1e74336c3b7c245c6e2a20d720e8e7a169de96317cf9 Usage terms US government public domain
eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:8091
Sources EV-23ca0495ceeaa40fbbd0b68b Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 8717f0f15f450dc6794ddee6aa2738ac3936f47918300d7d3cc5dd7f663a8238 Usage terms US government public domain
Observations for this power asset View on the global map Source snapshots by date · USA · eia860 Intercession City / P1 Generator · Operations
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Utility ID 6455 Utility Name Duke Energy Florida, LLC Plant Code 8049 Plant Name Intercession City State FL County Osceola Generator ID P1 Technology Petroleum Liquids Prime Mover GT Ownership S Duct Burners X Can Bypass Heat Recovery Steam Generator? X Nameplate Capacity (MW) 56.7 Nameplate Power Factor 0.9 Summer Capacity (MW) 45 Winter Capacity (MW) 60 Minimum Load (MW) 30 Uprate or Derate Completed During Year N Status OP Synchronized to Transmission Grid X Operating Month 5 Operating Year 1974 Associated with Combined Heat and Power System N Sector Name Electric Utility Sector 1 Topping or Bottoming X Energy Source 1 DFO Solid Fuel Gasification System? N Carbon Capture Technology? N Time from Cold Shutdown to Full Load 10M Multiple Fuels? N Original text OP source_record_id 3_1_Generator_Y2025.xlsx#Operable:8089
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Operable:8089
Sources EV-ebe46476b34ef779d52ba420 Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 5a75b7a7b74aef5827fa1e74336c3b7c245c6e2a20d720e8e7a169de96317cf9 Usage terms US government public domain
Observations for this power asset Source snapshots by date · USA · eia860m Intercession City / P1 Generator · Operations
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Entity ID 6455 Entity Name Duke Energy Florida, LLC Plant ID 8049 Plant Name Intercession City Google Map Map Bing Map Map Plant State FL County Osceola Balancing Authority Code FPC Sector Electric Utility Generator ID P1 Nameplate Capacity (MW) 56.7 Net Summer Capacity (MW) 45 Net Winter Capacity (MW) 60 Technology Petroleum Liquids Energy Source Code DFO Prime Mover Code GT Operating Month 5 Operating Year 1974 Status (OP) Operating Latitude 28.262778 Longitude -81.54861 Original text (OP) Operating source_record_id Operating:8091
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:8091
Sources EV-23ca0495ceeaa40fbbd0b68b Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 8717f0f15f450dc6794ddee6aa2738ac3936f47918300d7d3cc5dd7f663a8238 Usage terms US government public domain
Observations for this power asset