Power assets and projects · USA · eia860m

Belleville Dam / 2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)21 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-5609538b4eebf80cbc2e6245
Net Summer Capacity (MW)21 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-5609538b4eebf80cbc2e6245
Net Winter Capacity (MW)21 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-5609538b4eebf80cbc2e6245
Detailed source fields
Original source fieldPublished value or condition
Entity ID40577
Entity NameAmerican Mun Power-Ohio, Inc
Plant ID7594
Plant NameBelleville Dam
Google MapMap
Bing MapMap
Plant StateWV
CountyWood
Balancing Authority CodePJM
SectorElectric Utility
Generator ID2
Nameplate Capacity (MW)21
Net Summer Capacity (MW)21
Net Winter Capacity (MW)21
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month6
Operating Year1999
Status(OP) Operating
Latitude39.1192
Longitude-81.7375
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:7418

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:7416

Sources EV-e97ea7b81aa012584afb4b07
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 2a3d22433f8c7ed7140c5d503c03a1ccb8c7fcbf44e86bba6735b8622d604b81

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:7418

Sources EV-5609538b4eebf80cbc2e6245
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 3c650183229bad7ea4e01ec6a973206274968d37b90347bd11b74f27a6657dd8

Usage terms US government public domain

Source snapshots by date · USA · eia860

Belleville Dam / 2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID40577
Utility NameAmerican Mun Power-Ohio, Inc
Plant Code7594
Plant NameBelleville Dam
StateWV
CountyWood
Generator ID2
TechnologyConventional Hydroelectric
Prime MoverHY
OwnershipJ
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
RTO/ISO LMP Node DesignationBELLEV12
RTO/ISO Location Designation for Reporting Wholesale Sales Data to FERCBELLEV12
Nameplate Capacity (MW)21
Nameplate Power Factor0.9
Summer Capacity (MW)21
Winter Capacity (MW)21
Minimum Load (MW)3
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month6
Operating Year1999
Associated with Combined Heat and Power SystemN
Sector NameElectric Utility
Sector1
Topping or BottomingX
Energy Source 1WAT
Solid Fuel Gasification System?N
Carbon Capture Technology?N
Turbines or Hydrokinetic Buoys0
Time from Cold Shutdown to Full Load10M
Multiple Fuels?N
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:7416

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:7416

Sources EV-e97ea7b81aa012584afb4b07
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 2a3d22433f8c7ed7140c5d503c03a1ccb8c7fcbf44e86bba6735b8622d604b81

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Belleville Dam / 2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID40577
Entity NameAmerican Mun Power-Ohio, Inc
Plant ID7594
Plant NameBelleville Dam
Google MapMap
Bing MapMap
Plant StateWV
CountyWood
Balancing Authority CodePJM
SectorElectric Utility
Generator ID2
Nameplate Capacity (MW)21
Net Summer Capacity (MW)21
Net Winter Capacity (MW)21
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month6
Operating Year1999
Status(OP) Operating
Latitude39.1192
Longitude-81.7375
Original text(OP) Operating
source_record_idOperating:7418

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:7418

Sources EV-5609538b4eebf80cbc2e6245
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 3c650183229bad7ea4e01ec6a973206274968d37b90347bd11b74f27a6657dd8

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel