Power assets and projects · USA · eia860m

Concord / 2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)95.4 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-5db9cfa00b5772708de10f15
Net Summer Capacity (MW)89.8 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-5db9cfa00b5772708de10f15
Net Winter Capacity (MW)100 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-5db9cfa00b5772708de10f15
Detailed source fields
Original source fieldPublished value or condition
Entity ID20847
Entity NameWisconsin Electric Power Co
Plant ID7159
Plant NameConcord
Google MapMap
Bing MapMap
Plant StateWI
CountyJefferson
Balancing Authority CodeMISO
SectorElectric Utility
Generator ID2
Nameplate Capacity (MW)95.4
Net Summer Capacity (MW)89.8
Net Winter Capacity (MW)100
TechnologyNatural Gas Fired Combustion Turbine
Energy Source CodeNG
Prime Mover CodeGT
Operating Month7
Operating Year1993
Status(OP) Operating
Latitude43.1669
Longitude-88.69
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:7002

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:7006

Sources EV-47f1f3f47e9614ccb2e51343
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 2eba605a3b0eb5a9bd222338ec5ac9753578c7a57485156b25864642d428c8a2

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:7002

Sources EV-5db9cfa00b5772708de10f15
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 40d0ebed4f86a100fec00932996be9593cc140d394d389f8a61ed0cac4c4865d

Usage terms US government public domain

Source snapshots by date · USA · eia860

Concord / 2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID20847
Utility NameWisconsin Electric Power Co
Plant Code7159
Plant NameConcord
StateWI
CountyJefferson
Generator ID2
TechnologyNatural Gas Fired Combustion Turbine
Prime MoverGT
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
RTO/ISO LMP Node DesignationWEC.CCDGTC2
RTO/ISO Location Designation for Reporting Wholesale Sales Data to FERCWEC.CCDGTC2
Nameplate Capacity (MW)95.4
Nameplate Power Factor0.8
Summer Capacity (MW)89.8
Winter Capacity (MW)100
Minimum Load (MW)50
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month7
Operating Year1993
Associated with Combined Heat and Power SystemN
Sector NameElectric Utility
Sector1
Topping or BottomingX
Energy Source 1NG
Energy Source 2DFO
Solid Fuel Gasification System?N
Carbon Capture Technology?N
Time from Cold Shutdown to Full Load1H
Other Planned Modifications?N
Multiple Fuels?Y
Cofire Fuels?N
Switch Between Oil and Natural Gas?Y
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:7006

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:7006

Sources EV-47f1f3f47e9614ccb2e51343
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 2eba605a3b0eb5a9bd222338ec5ac9753578c7a57485156b25864642d428c8a2

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Concord / 2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID20847
Entity NameWisconsin Electric Power Co
Plant ID7159
Plant NameConcord
Google MapMap
Bing MapMap
Plant StateWI
CountyJefferson
Balancing Authority CodeMISO
SectorElectric Utility
Generator ID2
Nameplate Capacity (MW)95.4
Net Summer Capacity (MW)89.8
Net Winter Capacity (MW)100
TechnologyNatural Gas Fired Combustion Turbine
Energy Source CodeNG
Prime Mover CodeGT
Operating Month7
Operating Year1993
Status(OP) Operating
Latitude43.1669
Longitude-88.69
Original text(OP) Operating
source_record_idOperating:7002

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:7002

Sources EV-5db9cfa00b5772708de10f15
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 40d0ebed4f86a100fec00932996be9593cc140d394d389f8a61ed0cac4c4865d

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel