POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

DEL022-30423B Thorogoods Rd, LLC / DEL22

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)2 MWOriginal source column definition · Generator · (V) Under construction, more than 50 percent complete
As-of date 2026-08
Sources EV-32e3b2242141aca80c247d28
Net Summer Capacity (MW)2 MWOriginal source column definition · Generator · (V) Under construction, more than 50 percent complete
As-of date 2026-08
Sources EV-32e3b2242141aca80c247d28
Net Winter Capacity (MW)2 MWOriginal source column definition · Generator · (V) Under construction, more than 50 percent complete
As-of date 2026-08
Sources EV-32e3b2242141aca80c247d28
Detailed source fields
Original source fieldPublished value or condition
Entity ID65539
Entity NamePivot Energy
Plant ID70196
Plant NameDEL022-30423B Thorogoods Rd, LLC
Google MapMap
Bing MapMap
Plant StateDE
CountySussex
Balancing Authority CodePJM
SectorIPP Non-CHP
Generator IDDEL22
Nameplate Capacity (MW)2
Net Summer Capacity (MW)2
Net Winter Capacity (MW)2
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Planned Operation Month1
Planned Operation Year2027
Status(V) Under construction, more than 50 percent complete
Latitude38.569503
Longitude-75.26468
Original text(V) Under construction, more than 50 percent complete
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idPlanned:644

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:2658

Sources EV-0c4c174d6ad0eac00213a792
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 4ba57c8684de5a945a76c0a167357cac1561dd4810122fd74dd4f0f00a36b335

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:644

Sources EV-32e3b2242141aca80c247d28
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 cae4fc03fd9dd42e90733ab230d4ff4aa54d6a892d09a3bbcfd861fb2945002e

Usage terms US government public domain

Source snapshots by date · USA · eia860

DEL022-30423B Thorogoods Rd, LLC / DEL22

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID65539
Utility NamePivot Energy
Plant Code70196
Plant NameDEL022-30423B Thorogoods Rd, LLC
StateDE
CountySussex
Generator IDDEL22
TechnologySolar Photovoltaic
Prime MoverPV
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)2
Summer Capacity (MW)2
Winter Capacity (MW)2
StatusV
Effective Month9
Effective Year2026
Current Month1
Current Year2027
Associated with Combined Heat and Power SystemN
Sector NameIPP Non-CHP
Sector2
Previously CanceledN
Energy Source 1SUN
Original textV
source_record_id3_1_Generator_Y2025.xlsx#Proposed:2658

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:2658

Sources EV-0c4c174d6ad0eac00213a792
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 4ba57c8684de5a945a76c0a167357cac1561dd4810122fd74dd4f0f00a36b335

Usage terms US government public domain

Source snapshots by date · USA · eia860m

DEL022-30423B Thorogoods Rd, LLC / DEL22

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID65539
Entity NamePivot Energy
Plant ID70196
Plant NameDEL022-30423B Thorogoods Rd, LLC
Google MapMap
Bing MapMap
Plant StateDE
CountySussex
Balancing Authority CodePJM
SectorIPP Non-CHP
Generator IDDEL22
Nameplate Capacity (MW)2
Net Summer Capacity (MW)2
Net Winter Capacity (MW)2
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Planned Operation Month1
Planned Operation Year2027
Status(V) Under construction, more than 50 percent complete
Latitude38.569503
Longitude-75.26468
Original text(V) Under construction, more than 50 percent complete
source_record_idPlanned:644

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:644

Sources EV-32e3b2242141aca80c247d28
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 cae4fc03fd9dd42e90733ab230d4ff4aa54d6a892d09a3bbcfd861fb2945002e

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel