POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Grant Solar, LLC / GRNTS

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)99 MWOriginal source column definition · Generator · (L) Regulatory approvals pending. Not under construction
As-of date 2026-08
Sources EV-f9a0ea2ac7c2dbbda6637d01
Net Summer Capacity (MW)99 MWOriginal source column definition · Generator · (L) Regulatory approvals pending. Not under construction
As-of date 2026-08
Sources EV-f9a0ea2ac7c2dbbda6637d01
Net Winter Capacity (MW)99 MWOriginal source column definition · Generator · (L) Regulatory approvals pending. Not under construction
As-of date 2026-08
Sources EV-f9a0ea2ac7c2dbbda6637d01
Detailed source fields
Original source fieldPublished value or condition
Entity ID62759
Entity NameGeronimo Power
Plant ID69981
Plant NameGrant Solar, LLC
Google MapMap
Bing MapMap
Plant StateSD
CountyMcCook
Balancing Authority CodeMISO
SectorIPP Non-CHP
Generator IDGRNTS
Nameplate Capacity (MW)99
Net Summer Capacity (MW)99
Net Winter Capacity (MW)99
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Planned Operation Month10
Planned Operation Year2027
Status(L) Regulatory approvals pending. Not under construction
Latitude43.550003
Longitude-97.26738
Original text(L) Regulatory approvals pending. Not under construction
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idPlanned:1110

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:2504

Sources EV-49300a65db0755996a46c967
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 0de9a48a95284b1096621eafcc0930f1d80de9f2e92499f58c8b93af1cafb2ab

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:1110

Sources EV-f9a0ea2ac7c2dbbda6637d01
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 2629fa706a77c2336e5e7410f023208f47c2e7e80051685f94b158b76bee0f26

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Grant Solar, LLC / GRNTS

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID62759
Entity NameGeronimo Power
Plant ID69981
Plant NameGrant Solar, LLC
Google MapMap
Bing MapMap
Plant StateSD
CountyMcCook
Balancing Authority CodeMISO
SectorIPP Non-CHP
Generator IDGRNTS
Nameplate Capacity (MW)99
Net Summer Capacity (MW)99
Net Winter Capacity (MW)99
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Planned Operation Month10
Planned Operation Year2027
Status(L) Regulatory approvals pending. Not under construction
Latitude43.550003
Longitude-97.26738
Original text(L) Regulatory approvals pending. Not under construction
source_record_idPlanned:1110

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:1110

Sources EV-f9a0ea2ac7c2dbbda6637d01
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 2629fa706a77c2336e5e7410f023208f47c2e7e80051685f94b158b76bee0f26

Usage terms US government public domain

Source snapshots by date · USA · eia860

Grant Solar, LLC / GRNTS

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID62759
Utility NameGeronimo Power
Plant Code69981
Plant NameGrant Solar, LLC
StateSD
CountyMcCook
Generator IDGRNTS
TechnologySolar Photovoltaic
Prime MoverPV
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)99
Summer Capacity (MW)99
Winter Capacity (MW)99
StatusL
Effective Month10
Effective Year2027
Current Month10
Current Year2027
Sector NameIPP Non-CHP
Sector2
Previously CanceledN
Energy Source 1SUN
Original textL
source_record_id3_1_Generator_Y2025.xlsx#Proposed:2504

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:2504

Sources EV-49300a65db0755996a46c967
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 0de9a48a95284b1096621eafcc0930f1d80de9f2e92499f58c8b93af1cafb2ab

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel