Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 3items · current page 1–3 · Source records, not unique facilities.
Power assets and projects · USA · eia860m
Tanglewood BESS / BAT1
Generator · Plan
Metric or condition
Source value
Basis, scope and stage
Nameplate Capacity (MW)
3.9 MW
Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-02e3b82f1ee79bf990c8dabb
Net Summer Capacity (MW)
3.9 MW
Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-02e3b82f1ee79bf990c8dabb
Net Winter Capacity (MW)
3.9 MW
Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-02e3b82f1ee79bf990c8dabb
Detailed source fields
Original source field
Published value or condition
Entity ID
13683
Entity Name
North Carolina El Member Corp
Plant ID
69871
Plant Name
Tanglewood BESS
Google Map
Map
Bing Map
Map
Plant State
NC
County
Pasquotank
Balancing Authority Code
PJM
Sector
Electric Utility
Generator ID
BAT1
Nameplate Capacity (MW)
3.9
Net Summer Capacity (MW)
3.9
Net Winter Capacity (MW)
3.9
Technology
Batteries
Energy Source Code
MWH
Prime Mover Code
BA
Planned Operation Month
12
Planned Operation Year
2026
Status
(V) Under construction, more than 50 percent complete
Latitude
36.272111
Longitude
-76.30127
Original text
(V) Under construction, more than 50 percent complete