POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Deckerville Solar Park / DKVSP

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)200 MWOriginal source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete
As-of date 2026-08
Sources EV-9a6dafe7812e379cd265e896
Net Summer Capacity (MW)200 MWOriginal source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete
As-of date 2026-08
Sources EV-9a6dafe7812e379cd265e896
Net Winter Capacity (MW)200 MWOriginal source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete
As-of date 2026-08
Sources EV-9a6dafe7812e379cd265e896
Detailed source fields
Original source fieldPublished value or condition
Entity ID5109
Entity NameDTE Electric Company
Plant ID69776
Plant NameDeckerville Solar Park
Google MapMap
Bing MapMap
Plant StateMI
CountySanilac
Balancing Authority CodeMISO
SectorElectric Utility
Generator IDDKVSP
Nameplate Capacity (MW)200
Net Summer Capacity (MW)200
Net Winter Capacity (MW)200
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Planned Operation Month11
Planned Operation Year2028
Status(U) Under construction, less than or equal to 50 percent complete
Latitude44.5521
Longitude-82.7649
Original text(U) Under construction, less than or equal to 50 percent complete
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idPlanned:1730

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:2161

Sources EV-b5ef93fb50ae890a096d75ab
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 22cb48f29ef7710adb1dfdc7cfa35c6934889bede1c653ff49439046ab258421

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:1730

Sources EV-9a6dafe7812e379cd265e896
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 4447cbed794852c9a8f4ca14cb2719326e1985ea772f6c7d3a05f7c76bb8ecf0

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Deckerville Solar Park / DKVSP

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID5109
Entity NameDTE Electric Company
Plant ID69776
Plant NameDeckerville Solar Park
Google MapMap
Bing MapMap
Plant StateMI
CountySanilac
Balancing Authority CodeMISO
SectorElectric Utility
Generator IDDKVSP
Nameplate Capacity (MW)200
Net Summer Capacity (MW)200
Net Winter Capacity (MW)200
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Planned Operation Month11
Planned Operation Year2028
Status(U) Under construction, less than or equal to 50 percent complete
Latitude44.5521
Longitude-82.7649
Original text(U) Under construction, less than or equal to 50 percent complete
source_record_idPlanned:1730

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:1730

Sources EV-9a6dafe7812e379cd265e896
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 4447cbed794852c9a8f4ca14cb2719326e1985ea772f6c7d3a05f7c76bb8ecf0

Usage terms US government public domain

Source snapshots by date · USA · eia860

Deckerville Solar Park / DKVSP

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID5109
Utility NameDTE Electric Company
Plant Code69776
Plant NameDeckerville Solar Park
StateMI
CountySanilac
Generator IDDKVSP
TechnologySolar Photovoltaic
Prime MoverPV
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)200
Summer Capacity (MW)200
Winter Capacity (MW)200
StatusU
Effective Month11
Effective Year2028
Current Month11
Current Year2028
Sector NameElectric Utility
Sector1
Previously CanceledN
Energy Source 1SUN
Original textU
source_record_id3_1_Generator_Y2025.xlsx#Proposed:2161

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:2161

Sources EV-b5ef93fb50ae890a096d75ab
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 22cb48f29ef7710adb1dfdc7cfa35c6934889bede1c653ff49439046ab258421

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel