Power assets and projects · USA · eia860m
Rock Island Generation Project / RIG3
Generator · Plan
Metric or condition
Source value
Basis, scope and stage
Nameplate Capacity (MW)
20.3 MW
Original source column definition · Generator · (L) Regulatory approvals pending. Not under construction As-of date 2026-08 Sources EV-cbd815fb8d3250c14a8beec4
Net Summer Capacity (MW)
19.9 MW
Original source column definition · Generator · (L) Regulatory approvals pending. Not under construction As-of date 2026-08 Sources EV-cbd815fb8d3250c14a8beec4
Net Winter Capacity (MW)
19.9 MW
Original source column definition · Generator · (L) Regulatory approvals pending. Not under construction As-of date 2026-08 Sources EV-cbd815fb8d3250c14a8beec4
Detailed source fields
Original source field
Published value or condition
Entity ID
67625
Entity Name
Kerrville Public Utility Board Public Facility Corp
Plant ID
69760
Plant Name
Rock Island Generation Project
Google Map
Map
Bing Map
Map
Plant State
TX
County
Colorado
Balancing Authority Code
ERCO
Sector
Electric Utility
Generator ID
RIG3
Nameplate Capacity (MW)
20.3
Net Summer Capacity (MW)
19.9
Net Winter Capacity (MW)
19.9
Technology
Natural Gas Internal Combustion Engine
Energy Source Code
NG
Prime Mover Code
IC
Planned Operation Month
9
Planned Operation Year
2027
Status
(L) Regulatory approvals pending. Not under construction
Latitude
29.55068
Longitude
-96.53675
Original text
(L) Regulatory approvals pending. Not under construction