Power and Facility Evidence Database Review power assets, contract observations, facility specifications and relationships from public sources.
Global Facilities and Power Map Korea Site and Power Map Korea Data Center Database This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 3items · current page 1–3 · Source records, not unique facilities.
Power assets and projects · USA · eia860m Jumper Creek Solar Plant / JCSP1 Generator · Operations
Metric or condition Source value Basis, scope and stage Nameplate Capacity (MW) 74.9 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-0b90b4865a0008425e59e46f Net Summer Capacity (MW) 74.9 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-0b90b4865a0008425e59e46f Net Winter Capacity (MW) 74.9 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-0b90b4865a0008425e59e46f
Detailed source fields Original source field Published value or condition Entity ID 6455 Entity Name Duke Energy Florida, LLC Plant ID 69627 Plant Name Jumper Creek Solar Plant Google Map Map Bing Map Map Plant State FL County Sumter Balancing Authority Code FPC Sector Electric Utility Generator ID JCSP1 Nameplate Capacity (MW) 74.9 Net Summer Capacity (MW) 74.9 Net Winter Capacity (MW) 74.9 Technology Solar Photovoltaic Energy Source Code SUN Prime Mover Code PV Operating Month 4 Operating Year 2026 Status (OP) Operating Latitude 28.954544 Longitude -82.17652 Original text (OP) Operating Coordinate accuracy source_precision_not_independently_surveyed source_record_id Operating:27962
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Proposed:1993
Sources EV-fff4f7106b0c89794d187c30 Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 b9a5fc4f3de538f7d7da3afe9f4471076bb9c9e65b637fb7412ec81517ea75a1 Usage terms US government public domain
eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:27962
Sources EV-0b90b4865a0008425e59e46f Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 5311c1102d119c8e70bda1dbb4705cb45b100e76f5a2680f358fecf92bf61008 Usage terms US government public domain
Observations for this power asset View on the global map Source snapshots by date · USA · eia860 Jumper Creek Solar Plant / JCSP1 Generator · Plan
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Utility ID 6455 Utility Name Duke Energy Florida, LLC Plant Code 69627 Plant Name Jumper Creek Solar Plant State FL County Sumter Generator ID JCSP1 Technology Solar Photovoltaic Prime Mover PV Ownership S Duct Burners X Can Bypass Heat Recovery Steam Generator? X Nameplate Capacity (MW) 74.9 Summer Capacity (MW) 74.9 Winter Capacity (MW) 74.9 Status V Effective Month 5 Effective Year 2026 Current Month 4 Current Year 2026 Associated with Combined Heat and Power System N Sector Name Electric Utility Sector 1 Previously Canceled N Energy Source 1 SUN Original text V source_record_id 3_1_Generator_Y2025.xlsx#Proposed:1993
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Proposed:1993
Sources EV-fff4f7106b0c89794d187c30 Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 b9a5fc4f3de538f7d7da3afe9f4471076bb9c9e65b637fb7412ec81517ea75a1 Usage terms US government public domain
Observations for this power asset Source snapshots by date · USA · eia860m Jumper Creek Solar Plant / JCSP1 Generator · Operations
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Entity ID 6455 Entity Name Duke Energy Florida, LLC Plant ID 69627 Plant Name Jumper Creek Solar Plant Google Map Map Bing Map Map Plant State FL County Sumter Balancing Authority Code FPC Sector Electric Utility Generator ID JCSP1 Nameplate Capacity (MW) 74.9 Net Summer Capacity (MW) 74.9 Net Winter Capacity (MW) 74.9 Technology Solar Photovoltaic Energy Source Code SUN Prime Mover Code PV Operating Month 4 Operating Year 2026 Status (OP) Operating Latitude 28.954544 Longitude -82.17652 Original text (OP) Operating source_record_id Operating:27962
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:27962
Sources EV-0b90b4865a0008425e59e46f Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 5311c1102d119c8e70bda1dbb4705cb45b100e76f5a2680f358fecf92bf61008 Usage terms US government public domain