Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 3items · current page 1–3 · Source records, not unique facilities.
Power assets and projects · USA · eia860m
Keene Branch Solar / 1
Generator · Plan
Metric or condition
Source value
Basis, scope and stage
Nameplate Capacity (MW)
74.5 MW
Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-fd37cf7831801b98529d6f63
Net Summer Capacity (MW)
74.5 MW
Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-fd37cf7831801b98529d6f63
Net Winter Capacity (MW)
74.5 MW
Original source column definition · Generator · (V) Under construction, more than 50 percent complete As-of date 2026-08 Sources EV-fd37cf7831801b98529d6f63
Detailed source fields
Original source field
Published value or condition
Entity ID
18454
Entity Name
Tampa Electric Co
Plant ID
69461
Plant Name
Keene Branch Solar
Google Map
Map
Bing Map
Map
Plant State
FL
County
Hillsborough
Balancing Authority Code
TEC
Sector
Electric Utility
Generator ID
1
Nameplate Capacity (MW)
74.5
Net Summer Capacity (MW)
74.5
Net Winter Capacity (MW)
74.5
Technology
Solar Photovoltaic
Energy Source Code
SUN
Prime Mover Code
PV
Planned Operation Month
12
Planned Operation Year
2026
Status
(V) Under construction, more than 50 percent complete
Latitude
27.658706
Longitude
-82.2657
Original text
(V) Under construction, more than 50 percent complete