Power assets and projects · USA · eia860m
Asheville BESS / AVLB1
Generator · Plan
Metric or condition
Source value
Basis, scope and stage
Nameplate Capacity (MW)
17.3 MW
Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-883c90e1098d2337a122f3cd
Net Summer Capacity (MW)
17.3 MW
Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-883c90e1098d2337a122f3cd
Net Winter Capacity (MW)
17.3 MW
Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-883c90e1098d2337a122f3cd
Detailed source fields
Original source field
Published value or condition
Entity ID
3046
Entity Name
Duke Energy Progress - (NC)
Plant ID
69429
Plant Name
Asheville BESS
Google Map
Map
Bing Map
Map
Plant State
NC
County
Buncombe
Balancing Authority Code
CPLW
Sector
Electric Utility
Generator ID
AVLB1
Nameplate Capacity (MW)
17.3
Net Summer Capacity (MW)
17.3
Net Winter Capacity (MW)
17.3
Technology
Batteries
Energy Source Code
MWH
Prime Mover Code
BA
Planned Operation Month
9
Planned Operation Year
2026
Status
(U) Under construction, less than or equal to 50 percent complete
Latitude
35.472139
Longitude
-82.54163
Original text
(U) Under construction, less than or equal to 50 percent complete