Power assets and projects · USA · eia860m
Sawtooth Solar / STBA
Generator · Plan
Metric or condition
Source value
Basis, scope and stage
Nameplate Capacity (MW)
250 MW
Original source column definition · Generator · (L) Regulatory approvals pending. Not under construction As-of date 2026-08 Sources EV-f764f6c0d41dd8eeb19397f2
Net Summer Capacity (MW)
250 MW
Original source column definition · Generator · (L) Regulatory approvals pending. Not under construction As-of date 2026-08 Sources EV-f764f6c0d41dd8eeb19397f2
Net Winter Capacity (MW)
250 MW
Original source column definition · Generator · (L) Regulatory approvals pending. Not under construction As-of date 2026-08 Sources EV-f764f6c0d41dd8eeb19397f2
Detailed source fields
Original source field
Published value or condition
Entity ID
64452
Entity Name
EDF Renewables Development, Inc.
Plant ID
68883
Plant Name
Sawtooth Solar
Google Map
Map
Bing Map
Map
Plant State
AZ
County
Pinal
Balancing Authority Code
AZPS
Sector
IPP Non-CHP
Generator ID
STBA
Nameplate Capacity (MW)
250
Net Summer Capacity (MW)
250
Net Winter Capacity (MW)
250
Technology
Batteries
Energy Source Code
MWH
Prime Mover Code
BA
Planned Operation Month
6
Planned Operation Year
2028
Status
(L) Regulatory approvals pending. Not under construction
Latitude
32.728
Longitude
-111.629
Original text
(L) Regulatory approvals pending. Not under construction