Power assets and projects · USA · eia860m

Smarr Combined Cycle Energy Facility / 2

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)345 MWOriginal source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated
As-of date 2026-08
Sources EV-48a2e0e93ccfe47797f4b01b
Net Summer Capacity (MW)304 MWOriginal source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated
As-of date 2026-08
Sources EV-48a2e0e93ccfe47797f4b01b
Net Winter Capacity (MW)309 MWOriginal source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated
As-of date 2026-08
Sources EV-48a2e0e93ccfe47797f4b01b
Detailed source fields
Original source fieldPublished value or condition
Entity ID13994
Entity NameOglethorpe Power Corporation
Plant ID68546
Plant NameSmarr Combined Cycle Energy Facility
Google MapMap
Bing MapMap
Plant StateGA
CountyMonroe
Balancing Authority CodeSOCO
SectorElectric Utility
Generator ID2
Unit Code1
Nameplate Capacity (MW)345
Net Summer Capacity (MW)304
Net Winter Capacity (MW)309
TechnologyNatural Gas Fired Combined Cycle
Energy Source CodeNG
Prime Mover CodeCC
Planned Operation Month6
Planned Operation Year2029
Status(P) Planned for installation, but regulatory approvals not initiated
Latitude32.975936
Longitude-83.84369
Original text(P) Planned for installation, but regulatory approvals not initiated
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idPlanned:1917

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:1392

Sources EV-399c2581f43fe3dd95170ff8
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 8d54c0047888eddae753a6b68da374c3ba59edb50b6a69700b2dc493a33557fa

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:1917

Sources EV-48a2e0e93ccfe47797f4b01b
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 3e32170b6f0bfd35898c95a359d6417961206eeabe356481df5e5a4fcfa1bc21

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Smarr Combined Cycle Energy Facility / 2

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID13994
Entity NameOglethorpe Power Corporation
Plant ID68546
Plant NameSmarr Combined Cycle Energy Facility
Google MapMap
Bing MapMap
Plant StateGA
CountyMonroe
Balancing Authority CodeSOCO
SectorElectric Utility
Generator ID2
Unit Code1
Nameplate Capacity (MW)345
Net Summer Capacity (MW)304
Net Winter Capacity (MW)309
TechnologyNatural Gas Fired Combined Cycle
Energy Source CodeNG
Prime Mover CodeCC
Planned Operation Month6
Planned Operation Year2029
Status(P) Planned for installation, but regulatory approvals not initiated
Latitude32.975936
Longitude-83.84369
Original text(P) Planned for installation, but regulatory approvals not initiated
source_record_idPlanned:1917

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:1917

Sources EV-48a2e0e93ccfe47797f4b01b
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 3e32170b6f0bfd35898c95a359d6417961206eeabe356481df5e5a4fcfa1bc21

Usage terms US government public domain

Source snapshots by date · USA · eia860

Smarr Combined Cycle Energy Facility / 2

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID13994
Utility NameOglethorpe Power Corporation
Plant Code68546
Plant NameSmarr Combined Cycle Energy Facility
StateGA
CountyMonroe
Generator ID2
TechnologyNatural Gas Fired Combined Cycle
Prime MoverCC
Unit Code1
OwnershipS
Duct BurnersY
Can Bypass Heat Recovery Steam Generator?N
Nameplate Capacity (MW)345
Nameplate Power Factor0.85
Summer Capacity (MW)304
Winter Capacity (MW)309
StatusP
Effective Month6
Effective Year2029
Current Month6
Current Year2029
Sector NameElectric Utility
Sector1
Previously CanceledN
Energy Source 1NG
Multiple Fuels?N
Switch Between Oil and Natural Gas?N
Cofire Fuels?N
Original textP
source_record_id3_1_Generator_Y2025.xlsx#Proposed:1392

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:1392

Sources EV-399c2581f43fe3dd95170ff8
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 8d54c0047888eddae753a6b68da374c3ba59edb50b6a69700b2dc493a33557fa

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel