Power assets and projects · USA · eia860m

McGrau Ford Battery Storage Facility / 2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)265 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-a7a4ebee9b24e16afd513fe1
Net Summer Capacity (MW)265 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-a7a4ebee9b24e16afd513fe1
Net Winter Capacity (MW)265 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-a7a4ebee9b24e16afd513fe1
Nameplate Energy Capacity (MWh)1060 MWhOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-a7a4ebee9b24e16afd513fe1
Detailed source fields
Original source fieldPublished value or condition
Entity ID7140
Entity NameGeorgia Power Co
Plant ID68512
Plant NameMcGrau Ford Battery Storage Facility
Google MapMap
Bing MapMap
Plant StateGA
CountyCherokee
Balancing Authority CodeSOCO
SectorElectric Utility
Generator ID2
Nameplate Capacity (MW)265
Net Summer Capacity (MW)265
Net Winter Capacity (MW)265
TechnologyBatteries
Energy Source CodeMWH
Prime Mover CodeBA
Operating Month8
Operating Year2026
Status(OP) Operating
Nameplate Energy Capacity (MWh)1060
Latitude34.324977
Longitude-84.3289
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:27088

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:1372

Sources EV-ae835410838b1f1e4f4f4462
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 d3a0658b248011d7e55abd55eac06c7b0aa9af7d97f61f5b57fddaac20fba78d

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:27088

Sources EV-a7a4ebee9b24e16afd513fe1
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 09cadae1c97f045d153e31a42df8ca956ff9c6d5480eed768f100d929ded790f

Usage terms US government public domain

Source snapshots by date · USA · eia860

McGrau Ford Battery Storage Facility / 2

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID7140
Utility NameGeorgia Power Co
Plant Code68512
Plant NameMcGrau Ford Battery Storage Facility
StateGA
CountyCherokee
Generator ID2
TechnologyBatteries
Prime MoverBA
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)265
Summer Capacity (MW)265
Winter Capacity (MW)265
StatusU
Effective Month10
Effective Year2026
Current Month8
Current Year2026
Sector NameElectric Utility
Sector1
Previously CanceledN
Energy Source 1MWH
Original textU
source_record_id3_1_Generator_Y2025.xlsx#Proposed:1372

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:1372

Sources EV-ae835410838b1f1e4f4f4462
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 d3a0658b248011d7e55abd55eac06c7b0aa9af7d97f61f5b57fddaac20fba78d

Usage terms US government public domain

Source snapshots by date · USA · eia860m

McGrau Ford Battery Storage Facility / 2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID7140
Entity NameGeorgia Power Co
Plant ID68512
Plant NameMcGrau Ford Battery Storage Facility
Google MapMap
Bing MapMap
Plant StateGA
CountyCherokee
Balancing Authority CodeSOCO
SectorElectric Utility
Generator ID2
Nameplate Capacity (MW)265
Net Summer Capacity (MW)265
Net Winter Capacity (MW)265
TechnologyBatteries
Energy Source CodeMWH
Prime Mover CodeBA
Operating Month8
Operating Year2026
Status(OP) Operating
Nameplate Energy Capacity (MWh)1060
Latitude34.324977
Longitude-84.3289
Original text(OP) Operating
source_record_idOperating:27088

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:27088

Sources EV-a7a4ebee9b24e16afd513fe1
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 09cadae1c97f045d153e31a42df8ca956ff9c6d5480eed768f100d929ded790f

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel