Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 3items · current page 1–3 · Source records, not unique facilities.
Power assets and projects · USA · eia860m
Eagle Eye Solar and Storage / EAGL1
Generator · Plan
Metric or condition
Source value
Basis, scope and stage
Nameplate Capacity (MW)
400 MW
Original source column definition · Generator · (L) Regulatory approvals pending. Not under construction As-of date 2026-08 Sources EV-f3800b1a0c7d2421ffb80c90
Net Summer Capacity (MW)
400 MW
Original source column definition · Generator · (L) Regulatory approvals pending. Not under construction As-of date 2026-08 Sources EV-f3800b1a0c7d2421ffb80c90
Net Winter Capacity (MW)
400 MW
Original source column definition · Generator · (L) Regulatory approvals pending. Not under construction As-of date 2026-08 Sources EV-f3800b1a0c7d2421ffb80c90
Detailed source fields
Original source field
Published value or condition
Entity ID
66681
Entity Name
EAGL bn, LLC
Plant ID
68287
Plant Name
Eagle Eye Solar and Storage
Google Map
Map
Bing Map
Map
Plant State
AZ
County
La Paz
Balancing Authority Code
WALC
Sector
IPP Non-CHP
Generator ID
EAGL1
Nameplate Capacity (MW)
400
Net Summer Capacity (MW)
400
Net Winter Capacity (MW)
400
Technology
Solar Photovoltaic
Energy Source Code
SUN
Prime Mover Code
PV
Planned Operation Month
5
Planned Operation Year
2028
Status
(L) Regulatory approvals pending. Not under construction
Latitude
33.727
Longitude
-112.881
Original text
(L) Regulatory approvals pending. Not under construction