POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Aurora Renewable Energy (Hybrid) / AURRE

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)50 MWOriginal source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated
As-of date 2026-08
Sources EV-b7c2b66ee1d4b350b61b0c53
Net Summer Capacity (MW)50 MWOriginal source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated
As-of date 2026-08
Sources EV-b7c2b66ee1d4b350b61b0c53
Net Winter Capacity (MW)50 MWOriginal source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated
As-of date 2026-08
Sources EV-b7c2b66ee1d4b350b61b0c53
Detailed source fields
Original source fieldPublished value or condition
Entity ID64545
Entity NameVesper Energy Development LLC
Plant ID67983
Plant NameAurora Renewable Energy (Hybrid)
Google MapMap
Bing MapMap
Plant StateCA
CountyStanislaus
Balancing Authority CodeBANC
SectorIPP Non-CHP
Generator IDAURRE
Nameplate Capacity (MW)50
Net Summer Capacity (MW)50
Net Winter Capacity (MW)50
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Planned Operation Month4
Planned Operation Year2028
Status(P) Planned for installation, but regulatory approvals not initiated
Latitude37.628805
Longitude-121.0714
Original text(P) Planned for installation, but regulatory approvals not initiated
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idPlanned:1501

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:987

Sources EV-24e4fce4eaef24fc09b98349
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 5748b73385c657b1af46aedabab031a76641ac07ad1a5423baba111ed95a6e21

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:1501

Sources EV-b7c2b66ee1d4b350b61b0c53
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 afa8520c81cb9d49561c51cc16b124cf8de5e507815e6ca0d5154a1f1efbe8f7

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Aurora Renewable Energy (Hybrid) / AURRE

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID64545
Entity NameVesper Energy Development LLC
Plant ID67983
Plant NameAurora Renewable Energy (Hybrid)
Google MapMap
Bing MapMap
Plant StateCA
CountyStanislaus
Balancing Authority CodeBANC
SectorIPP Non-CHP
Generator IDAURRE
Nameplate Capacity (MW)50
Net Summer Capacity (MW)50
Net Winter Capacity (MW)50
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Planned Operation Month4
Planned Operation Year2028
Status(P) Planned for installation, but regulatory approvals not initiated
Latitude37.628805
Longitude-121.0714
Original text(P) Planned for installation, but regulatory approvals not initiated
source_record_idPlanned:1501

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:1501

Sources EV-b7c2b66ee1d4b350b61b0c53
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 afa8520c81cb9d49561c51cc16b124cf8de5e507815e6ca0d5154a1f1efbe8f7

Usage terms US government public domain

Source snapshots by date · USA · eia860

Aurora Renewable Energy (Hybrid) / AURRE

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID64545
Utility NameVesper Energy Development LLC
Plant Code67983
Plant NameAurora Renewable Energy (Hybrid)
StateCA
CountyStanislaus
Generator IDAURRE
TechnologySolar Photovoltaic
Prime MoverPV
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)50
Summer Capacity (MW)50
Winter Capacity (MW)50
StatusP
Effective Month4
Effective Year2028
Current Month4
Current Year2028
Associated with Combined Heat and Power SystemN
Sector NameIPP Non-CHP
Sector2
Previously CanceledN
Energy Source 1SUN
Multiple Fuels?N
Original textP
source_record_id3_1_Generator_Y2025.xlsx#Proposed:987

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:987

Sources EV-24e4fce4eaef24fc09b98349
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 5748b73385c657b1af46aedabab031a76641ac07ad1a5423baba111ed95a6e21

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel