Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 3items · current page 1–3 · Source records, not unique facilities.
Power assets and projects · USA · eia860m
Timber Cove Solar / 59957
Generator · Plan
Metric or condition
Source value
Basis, scope and stage
Nameplate Capacity (MW)
100 MW
Original source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated As-of date 2026-08 Sources EV-f7c29ac0a86e9e1098a2707b
Net Summer Capacity (MW)
100 MW
Original source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated As-of date 2026-08 Sources EV-f7c29ac0a86e9e1098a2707b
Net Winter Capacity (MW)
100 MW
Original source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated As-of date 2026-08 Sources EV-f7c29ac0a86e9e1098a2707b
Detailed source fields
Original source field
Published value or condition
Entity ID
65837
Entity Name
Freestone Solar LLC
Plant ID
66922
Plant Name
Timber Cove Solar
Google Map
Map
Bing Map
Map
Plant State
TX
County
Freestone
Balancing Authority Code
ERCO
Sector
IPP Non-CHP
Generator ID
59957
Nameplate Capacity (MW)
100
Net Summer Capacity (MW)
100
Net Winter Capacity (MW)
100
Technology
Solar Photovoltaic
Energy Source Code
SUN
Prime Mover Code
PV
Planned Operation Month
5
Planned Operation Year
2028
Status
(P) Planned for installation, but regulatory approvals not initiated
Latitude
31.870589
Longitude
-96.15247
Original text
(P) Planned for installation, but regulatory approvals not initiated