POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Bonanza Solar and Storage Project / BZPV

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)300 MWOriginal source column definition · Generator · (L) Regulatory approvals pending. Not under construction
As-of date 2026-08
Sources EV-22f3430c27bcd15fd0b955a4
Net Summer Capacity (MW)300 MWOriginal source column definition · Generator · (L) Regulatory approvals pending. Not under construction
As-of date 2026-08
Sources EV-22f3430c27bcd15fd0b955a4
Net Winter Capacity (MW)240 MWOriginal source column definition · Generator · (L) Regulatory approvals pending. Not under construction
As-of date 2026-08
Sources EV-22f3430c27bcd15fd0b955a4
Detailed source fields
Original source fieldPublished value or condition
Entity ID64452
Entity NameEDF Renewables Development, Inc.
Plant ID66908
Plant NameBonanza Solar and Storage Project
Google MapMap
Bing MapMap
Plant StateNV
CountyClark
Balancing Authority CodeCISO
SectorIPP Non-CHP
Generator IDBZPV
Nameplate Capacity (MW)300
Net Summer Capacity (MW)300
Net Winter Capacity (MW)240
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Planned Operation Month12
Planned Operation Year2027
Status(L) Regulatory approvals pending. Not under construction
Latitude36.558
Longitude-115.799
Original text(L) Regulatory approvals pending. Not under construction
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idPlanned:1270

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:766

Sources EV-eab8d8f84e492eebf71b1e6c
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 9098535dfca138195c355dac6cb9f24a21394221aad488c8a0281eb3008c3887

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:1270

Sources EV-22f3430c27bcd15fd0b955a4
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 bae8caf676c7fe2c2510784dcc9cef95ba62c51186207bb4e77d83227f8d07c9

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Bonanza Solar and Storage Project / BZPV

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID64452
Entity NameEDF Renewables Development, Inc.
Plant ID66908
Plant NameBonanza Solar and Storage Project
Google MapMap
Bing MapMap
Plant StateNV
CountyClark
Balancing Authority CodeCISO
SectorIPP Non-CHP
Generator IDBZPV
Nameplate Capacity (MW)300
Net Summer Capacity (MW)300
Net Winter Capacity (MW)240
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Planned Operation Month12
Planned Operation Year2027
Status(L) Regulatory approvals pending. Not under construction
Latitude36.558
Longitude-115.799
Original text(L) Regulatory approvals pending. Not under construction
source_record_idPlanned:1270

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:1270

Sources EV-22f3430c27bcd15fd0b955a4
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 bae8caf676c7fe2c2510784dcc9cef95ba62c51186207bb4e77d83227f8d07c9

Usage terms US government public domain

Source snapshots by date · USA · eia860

Bonanza Solar and Storage Project / BZPV

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID64452
Utility NameEDF Renewables Development, Inc.
Plant Code66908
Plant NameBonanza Solar and Storage Project
StateNV
CountyClark
Generator IDBZPV
TechnologySolar Photovoltaic
Prime MoverPV
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)300
Summer Capacity (MW)300
Winter Capacity (MW)240
StatusL
Effective Month12
Effective Year2027
Current Month12
Current Year2027
Sector NameIPP Non-CHP
Sector2
Previously CanceledN
Energy Source 1SUN
Original textL
source_record_id3_1_Generator_Y2025.xlsx#Proposed:766

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:766

Sources EV-eab8d8f84e492eebf71b1e6c
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 9098535dfca138195c355dac6cb9f24a21394221aad488c8a0281eb3008c3887

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel