Power assets and projects · USA · eia860m
Accalia Point Solar, LLC / 66666
Generator · Plan
Metric or condition
Source value
Basis, scope and stage
Nameplate Capacity (MW)
190.5 MW
Original source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated As-of date 2026-08 Sources EV-3cf601085abb51177a64fd94
Net Summer Capacity (MW)
190.5 MW
Original source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated As-of date 2026-08 Sources EV-3cf601085abb51177a64fd94
Net Winter Capacity (MW)
190.5 MW
Original source column definition · Generator · (P) Planned for installation, but regulatory approvals not initiated As-of date 2026-08 Sources EV-3cf601085abb51177a64fd94
Detailed source fields
Original source field
Published value or condition
Entity ID
65687
Entity Name
Accalia Point Solar, LLC
Plant ID
66673
Plant Name
Accalia Point Solar, LLC
Google Map
Map
Bing Map
Map
Plant State
TX
County
Cameron
Balancing Authority Code
ERCO
Sector
IPP Non-CHP
Generator ID
66666
Nameplate Capacity (MW)
190.5
Net Summer Capacity (MW)
190.5
Net Winter Capacity (MW)
190.5
Technology
Solar Photovoltaic
Energy Source Code
SUN
Prime Mover Code
PV
Planned Operation Month
5
Planned Operation Year
2028
Status
(P) Planned for installation, but regulatory approvals not initiated
Latitude
26.098075
Longitude
-97.83752
Original text
(P) Planned for installation, but regulatory approvals not initiated