Power assets and projects · USA · eia860m

Hecate Energy Pulaski 1 / HEPU1

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)150 MWOriginal source column definition · Generator · (L) Regulatory approvals pending. Not under construction
As-of date 2026-08
Sources EV-045303aa1d38555c0acccf52
Net Summer Capacity (MW)150 MWOriginal source column definition · Generator · (L) Regulatory approvals pending. Not under construction
As-of date 2026-08
Sources EV-045303aa1d38555c0acccf52
Net Winter Capacity (MW)150 MWOriginal source column definition · Generator · (L) Regulatory approvals pending. Not under construction
As-of date 2026-08
Sources EV-045303aa1d38555c0acccf52
Detailed source fields
Original source fieldPublished value or condition
Entity ID64904
Entity NameAES Clean Energy
Plant ID65665
Plant NameHecate Energy Pulaski 1
Google MapMap
Bing MapMap
Plant StateVA
CountyPulaski
Balancing Authority CodePJM
SectorIPP Non-CHP
Generator IDHEPU1
Nameplate Capacity (MW)150
Net Summer Capacity (MW)150
Net Winter Capacity (MW)150
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Planned Operation Month4
Planned Operation Year2028
Status(L) Regulatory approvals pending. Not under construction
Latitude37.139595
Longitude-80.68741
Original text(L) Regulatory approvals pending. Not under construction
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idPlanned:1494

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:538

Sources EV-6184bc349aeeb7dbe355fb35
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 43c5432a4bd19ef92134fb4dd463d6bb72e79a7cf5743ff84fecd285826db14b

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:1494

Sources EV-045303aa1d38555c0acccf52
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 07b53a42f0ca55771dccf0077c4592120ca668c9db856ca88ff5fa191b9298a7

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Hecate Energy Pulaski 1 / HEPU1

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID64904
Entity NameAES Clean Energy
Plant ID65665
Plant NameHecate Energy Pulaski 1
Google MapMap
Bing MapMap
Plant StateVA
CountyPulaski
Balancing Authority CodePJM
SectorIPP Non-CHP
Generator IDHEPU1
Nameplate Capacity (MW)150
Net Summer Capacity (MW)150
Net Winter Capacity (MW)150
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Planned Operation Month4
Planned Operation Year2028
Status(L) Regulatory approvals pending. Not under construction
Latitude37.139595
Longitude-80.68741
Original text(L) Regulatory approvals pending. Not under construction
source_record_idPlanned:1494

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:1494

Sources EV-045303aa1d38555c0acccf52
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 07b53a42f0ca55771dccf0077c4592120ca668c9db856ca88ff5fa191b9298a7

Usage terms US government public domain

Source snapshots by date · USA · eia860

Hecate Energy Pulaski 1 / HEPU1

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID64904
Utility NameAES Clean Energy
Plant Code65665
Plant NameHecate Energy Pulaski 1
StateVA
CountyPulaski
Generator IDHEPU1
TechnologySolar Photovoltaic
Prime MoverPV
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)150
Nameplate Power Factor0.99
Summer Capacity (MW)150
Winter Capacity (MW)150
StatusL
Effective Month11
Effective Year2023
Current Month4
Current Year2028
Sector NameIPP Non-CHP
Sector2
Previously CanceledN
Energy Source 1SUN
Carbon Capture Technology?N
Multiple Fuels?N
Original textL
source_record_id3_1_Generator_Y2025.xlsx#Proposed:538

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:538

Sources EV-6184bc349aeeb7dbe355fb35
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 43c5432a4bd19ef92134fb4dd463d6bb72e79a7cf5743ff84fecd285826db14b

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel