POWER & FACILITY EVIDENCE
Power and Facility Evidence Database Review power assets, contract observations, facility specifications and relationships from public sources.
Global Facilities and Power Map Korea Site and Power Map 최신성·수집 확인 현황 부가요금·전국 설비 통계 국내 공급 여유·차단기·담당 연락처 한전 인근변전소 조회 전력 수요·비용·공급검토 설비·전력 품질 근거 Korea Data Center Database This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 3items · current page 1–3 · Source records, not unique facilities.
Power assets and projects · USA · eia860m Ross County Solar, LLC / ROSS Generator · Operations
Metric or condition Source value Basis, scope and stage Nameplate Capacity (MW) 120 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-ae8174e6afde53a08beccd45 Net Summer Capacity (MW) 120 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-ae8174e6afde53a08beccd45 Net Winter Capacity (MW) 120 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-ae8174e6afde53a08beccd45 DC Net Capacity (MW) 155.8 MWdc Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-ae8174e6afde53a08beccd45
Detailed source fields Original source field Published value or condition Entity ID 62759 Entity Name Geronimo Power Plant ID 65343 Plant Name Ross County Solar, LLC Google Map Map Bing Map Map Plant State OH County Ross Balancing Authority Code PJM Sector IPP Non-CHP Generator ID ROSS Nameplate Capacity (MW) 120 Net Summer Capacity (MW) 120 Net Winter Capacity (MW) 120 Technology Solar Photovoltaic Energy Source Code SUN Prime Mover Code PV Operating Month 1 Operating Year 2025 Status (OP) Operating DC Net Capacity (MW) 155.8 Latitude 39.325867 Longitude -83.35276 Original text (OP) Operating Coordinate accuracy source_precision_not_independently_surveyed source_record_id Operating:23922
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Operable:23905
Sources EV-26bbe84524de38e77b9b07ad Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 b6d5d20fec59abbc75c3220ea5df1cd5cc4b729b3d852de87a1e5cb3f84aa1fe Usage terms US government public domain
eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:23922
Sources EV-ae8174e6afde53a08beccd45 Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 7e03afd490eb1b3027503f5a113c7902d4b6d450ec2c1001ef5252574b834796 Usage terms US government public domain
Observations for this power asset View on the global map Source snapshots by date · USA · eia860m Ross County Solar, LLC / ROSS Generator · Operations
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Entity ID 62759 Entity Name Geronimo Power Plant ID 65343 Plant Name Ross County Solar, LLC Google Map Map Bing Map Map Plant State OH County Ross Balancing Authority Code PJM Sector IPP Non-CHP Generator ID ROSS Nameplate Capacity (MW) 120 Net Summer Capacity (MW) 120 Net Winter Capacity (MW) 120 Technology Solar Photovoltaic Energy Source Code SUN Prime Mover Code PV Operating Month 1 Operating Year 2025 Status (OP) Operating DC Net Capacity (MW) 155.8 Latitude 39.325867 Longitude -83.35276 Original text (OP) Operating source_record_id Operating:23922
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:23922
Sources EV-ae8174e6afde53a08beccd45 Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 7e03afd490eb1b3027503f5a113c7902d4b6d450ec2c1001ef5252574b834796 Usage terms US government public domain
Observations for this power asset Source snapshots by date · USA · eia860 Ross County Solar, LLC / ROSS Generator · Operations
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Utility ID 62759 Utility Name Geronimo Power Plant Code 65343 Plant Name Ross County Solar, LLC State OH County Ross Generator ID ROSS Technology Solar Photovoltaic Prime Mover PV Ownership S Duct Burners X Can Bypass Heat Recovery Steam Generator? X Nameplate Capacity (MW) 120 Summer Capacity (MW) 120 Winter Capacity (MW) 120 Uprate or Derate Completed During Year N Status OP Synchronized to Transmission Grid X Operating Month 1 Operating Year 2025 Associated with Combined Heat and Power System N Sector Name IPP Non-CHP Sector 2 Topping or Bottoming X Energy Source 1 SUN Original text OP source_record_id 3_1_Generator_Y2025.xlsx#Operable:23905
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Operable:23905
Sources EV-26bbe84524de38e77b9b07ad Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 b6d5d20fec59abbc75c3220ea5df1cd5cc4b729b3d852de87a1e5cb3f84aa1fe Usage terms US government public domain
Observations for this power asset