Power assets and projects · USA · eia860m

Calhoun County Solar Project / GEN1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)125 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-af388b7c3d860a5ac2fcad64
Net Summer Capacity (MW)125 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-af388b7c3d860a5ac2fcad64
Net Winter Capacity (MW)125 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-af388b7c3d860a5ac2fcad64
DC Net Capacity (MW)166.42 MWdcOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-af388b7c3d860a5ac2fcad64
Detailed source fields
Original source fieldPublished value or condition
Entity ID64904
Entity NameAES Clean Energy
Plant ID64452
Plant NameCalhoun County Solar Project
Google MapMap
Bing MapMap
Plant StateMI
CountyCalhoun
Balancing Authority CodeMISO
SectorIPP Non-CHP
Generator IDGEN1
Nameplate Capacity (MW)125
Net Summer Capacity (MW)125
Net Winter Capacity (MW)125
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Operating Month3
Operating Year2025
Status(OP) Operating
DC Net Capacity (MW)166.42
Latitude42.254
Longitude-84.813
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:22875

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:22862

Sources EV-2a04d80a1bface6dd36fa8b7
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 4784eb3b8cf7e9a445a7154bc9bf0286a5c84f49ea19915fd0cd440ee18f5b37

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:22875

Sources EV-af388b7c3d860a5ac2fcad64
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 eb6b6fe879f70740948235773f68ac230d1d450e15d2f167d2b6d887c138d8b1

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Calhoun County Solar Project / GEN1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID64904
Entity NameAES Clean Energy
Plant ID64452
Plant NameCalhoun County Solar Project
Google MapMap
Bing MapMap
Plant StateMI
CountyCalhoun
Balancing Authority CodeMISO
SectorIPP Non-CHP
Generator IDGEN1
Nameplate Capacity (MW)125
Net Summer Capacity (MW)125
Net Winter Capacity (MW)125
TechnologySolar Photovoltaic
Energy Source CodeSUN
Prime Mover CodePV
Operating Month3
Operating Year2025
Status(OP) Operating
DC Net Capacity (MW)166.42
Latitude42.254
Longitude-84.813
Original text(OP) Operating
source_record_idOperating:22875

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:22875

Sources EV-af388b7c3d860a5ac2fcad64
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 eb6b6fe879f70740948235773f68ac230d1d450e15d2f167d2b6d887c138d8b1

Usage terms US government public domain

Source snapshots by date · USA · eia860

Calhoun County Solar Project / GEN1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID64904
Utility NameAES Clean Energy
Plant Code64452
Plant NameCalhoun County Solar Project
StateMI
CountyCalhoun
Generator IDGEN1
TechnologySolar Photovoltaic
Prime MoverPV
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)125
Summer Capacity (MW)125
Winter Capacity (MW)125
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month3
Operating Year2025
Sector NameIPP Non-CHP
Sector2
Energy Source 1SUN
Carbon Capture Technology?N
Multiple Fuels?N
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:22862

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:22862

Sources EV-2a04d80a1bface6dd36fa8b7
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 4784eb3b8cf7e9a445a7154bc9bf0286a5c84f49ea19915fd0cd440ee18f5b37

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel