Aratina Solar Center 2 / 45MGB

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)113 MWOriginal source column definition · Generator · (V) Under construction, more than 50 percent complete
As-of date 2026-08
Sources EV-a15bbb97c7db37137d393c4b
Net Summer Capacity (MW)113 MWOriginal source column definition · Generator · (V) Under construction, more than 50 percent complete
As-of date 2026-08
Sources EV-a15bbb97c7db37137d393c4b
Net Winter Capacity (MW)113 MWOriginal source column definition · Generator · (V) Under construction, more than 50 percent complete
As-of date 2026-08
Sources EV-a15bbb97c7db37137d393c4b
Detailed source fields
Original source fieldPublished value or condition
Entity ID63825
Entity Name45MG 8me LLC
Plant ID64215
Plant NameAratina Solar Center 2
Google MapMap
Bing MapMap
Plant StateCA
CountyKern
Balancing Authority CodeCISO
SectorIPP Non-CHP
Generator ID45MGB
Nameplate Capacity (MW)113
Net Summer Capacity (MW)113
Net Winter Capacity (MW)113
TechnologyBatteries
Energy Source CodeMWH
Prime Mover CodeBA
Planned Operation Month12
Planned Operation Year2026
Status(V) Under construction, more than 50 percent complete
Latitude35.062965
Longitude-118.0878
Original text(V) Under construction, more than 50 percent complete
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idPlanned:452

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:430

Sources EV-6fa1caee31fd5a9c9fe73a2d
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 c346aeea24bf9984ba0d37cac016c1c181b311ba911e76da6c4d6ab492bc449a

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:452

Sources EV-a15bbb97c7db37137d393c4b
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 42fb74c77a527cc3b79c1746417e0fbe91ae99a01099bc2d13381f6462e70c6b

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Aratina Solar Center 2 / 45MGB

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID63825
Entity Name45MG 8me LLC
Plant ID64215
Plant NameAratina Solar Center 2
Google MapMap
Bing MapMap
Plant StateCA
CountyKern
Balancing Authority CodeCISO
SectorIPP Non-CHP
Generator ID45MGB
Nameplate Capacity (MW)113
Net Summer Capacity (MW)113
Net Winter Capacity (MW)113
TechnologyBatteries
Energy Source CodeMWH
Prime Mover CodeBA
Planned Operation Month12
Planned Operation Year2026
Status(V) Under construction, more than 50 percent complete
Latitude35.062965
Longitude-118.0878
Original text(V) Under construction, more than 50 percent complete
source_record_idPlanned:452

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:452

Sources EV-a15bbb97c7db37137d393c4b
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 42fb74c77a527cc3b79c1746417e0fbe91ae99a01099bc2d13381f6462e70c6b

Usage terms US government public domain

Source snapshots by date · USA · eia860

Aratina Solar Center 2 / 45MGB

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID63825
Utility Name45MG 8me LLC
Plant Code64215
Plant NameAratina Solar Center 2
StateCA
CountyKern
Generator ID45MGB
TechnologyBatteries
Prime MoverBA
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)113
Summer Capacity (MW)113
Winter Capacity (MW)113
StatusU
Effective Month6
Effective Year2023
Current Month12
Current Year2026
Sector NameIPP Non-CHP
Sector2
Previously CanceledN
Energy Source 1MWH
Original textU
source_record_id3_1_Generator_Y2025.xlsx#Proposed:430

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:430

Sources EV-6fa1caee31fd5a9c9fe73a2d
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 c346aeea24bf9984ba0d37cac016c1c181b311ba911e76da6c4d6ab492bc449a

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel