Equinix Great Oaks Blvd. Fuel Cell / EQ14B

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)2.1 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-ce0aeff58f276fb870d60552
Net Summer Capacity (MW)2.1 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-ce0aeff58f276fb870d60552
Net Winter Capacity (MW)2.1 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-ce0aeff58f276fb870d60552
Detailed source fields
Original source fieldPublished value or condition
Entity ID62150
Entity Name2016 ESA Project Company, LLC
Plant ID62702
Plant NameEquinix Great Oaks Blvd. Fuel Cell
Google MapMap
Bing MapMap
Plant StateCA
CountySanta Clara
Balancing Authority CodeCISO
SectorIPP Non-CHP
Generator IDEQ14B
Nameplate Capacity (MW)2.1
Net Summer Capacity (MW)2.1
Net Winter Capacity (MW)2.1
TechnologyOther Natural Gas
Energy Source CodeNG
Prime Mover CodeFC
Operating Month12
Operating Year2017
Status(OP) Operating
Latitude37.24097
Longitude-121.7826
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:21043

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:21038

Sources EV-5d2c6a98a863da75e11223c9
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 74025fa400f00d8d2858c40fab673e43cd4b73baa8cd59f88ad68dcb662dd8b9

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:21043

Sources EV-ce0aeff58f276fb870d60552
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 c0de7e20c7f5610fef23d7659e546d3e71c30ed3876b3ba3c8afb2b946279750

Usage terms US government public domain

Source snapshots by date · USA · eia860

Equinix Great Oaks Blvd. Fuel Cell / EQ14B

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID62150
Utility Name2016 ESA Project Company, LLC
Plant Code62702
Plant NameEquinix Great Oaks Blvd. Fuel Cell
StateCA
CountySanta Clara
Generator IDEQ14B
TechnologyOther Natural Gas
Prime MoverFC
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)2.1
Nameplate Power Factor0.99
Summer Capacity (MW)2.1
Winter Capacity (MW)2.1
Minimum Load (MW)2.1
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month12
Operating Year2017
Associated with Combined Heat and Power SystemN
Sector NameIPP Non-CHP
Sector2
Topping or BottomingX
Energy Source 1NG
Solid Fuel Gasification System?N
Carbon Capture Technology?N
Turbines or Hydrokinetic Buoys0
Time from Cold Shutdown to Full Load12H
Multiple Fuels?N
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:21038

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:21038

Sources EV-5d2c6a98a863da75e11223c9
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 74025fa400f00d8d2858c40fab673e43cd4b73baa8cd59f88ad68dcb662dd8b9

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Equinix Great Oaks Blvd. Fuel Cell / EQ14B

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID62150
Entity Name2016 ESA Project Company, LLC
Plant ID62702
Plant NameEquinix Great Oaks Blvd. Fuel Cell
Google MapMap
Bing MapMap
Plant StateCA
CountySanta Clara
Balancing Authority CodeCISO
SectorIPP Non-CHP
Generator IDEQ14B
Nameplate Capacity (MW)2.1
Net Summer Capacity (MW)2.1
Net Winter Capacity (MW)2.1
TechnologyOther Natural Gas
Energy Source CodeNG
Prime Mover CodeFC
Operating Month12
Operating Year2017
Status(OP) Operating
Latitude37.24097
Longitude-121.7826
Original text(OP) Operating
source_record_idOperating:21043

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:21043

Sources EV-ce0aeff58f276fb870d60552
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 c0de7e20c7f5610fef23d7659e546d3e71c30ed3876b3ba3c8afb2b946279750

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel