Noland Wastewater Treatment Plant Hybrid / FAYEB

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)6 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-8d76af5558a5710b30c3bd08
Net Summer Capacity (MW)6 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-8d76af5558a5710b30c3bd08
Net Winter Capacity (MW)6 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-8d76af5558a5710b30c3bd08
Nameplate Energy Capacity (MWh)13.1 MWhOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-8d76af5558a5710b30c3bd08
Detailed source fields
Original source fieldPublished value or condition
Entity ID61204
Entity NameToday's Power, Inc.
Plant ID62682
Plant NameNoland Wastewater Treatment Plant Hybrid
Google MapMap
Bing MapMap
Plant StateAR
CountyWashington
Balancing Authority CodeSWPP
SectorCommercial Non-CHP
Generator IDFAYEB
Nameplate Capacity (MW)6
Net Summer Capacity (MW)6
Net Winter Capacity (MW)6
TechnologyBatteries
Energy Source CodeMWH
Prime Mover CodeBA
Operating Month7
Operating Year2019
Status(OP) Operating
Nameplate Energy Capacity (MWh)13.1
Latitude36.082301
Longitude-94.06715
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:21019

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:21014

Sources EV-67d95f2f651242c1057c55c7
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 10c204e3d8ea252722056e790bd98a2e5bbce762f43ee4184861ebb2016977b7

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:21019

Sources EV-8d76af5558a5710b30c3bd08
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 e931b1bc604e414c499b8e1b0906f60876897da4ef83111f1cdc8cfec19234d6

Usage terms US government public domain

Source snapshots by date · USA · eia860

Noland Wastewater Treatment Plant Hybrid / FAYEB

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID61204
Utility NameToday's Power, Inc.
Plant Code62682
Plant NameNoland Wastewater Treatment Plant Hybrid
StateAR
CountyWashington
Generator IDFAYEB
TechnologyBatteries
Prime MoverBA
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)6
Summer Capacity (MW)6
Winter Capacity (MW)6
Minimum Load (MW)0.1
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month7
Operating Year2019
Associated with Combined Heat and Power SystemN
Sector NameCommercial Non-CHP
Sector4
Topping or BottomingX
Energy Source 1MWH
Time from Cold Shutdown to Full Load10M
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:21014

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:21014

Sources EV-67d95f2f651242c1057c55c7
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 10c204e3d8ea252722056e790bd98a2e5bbce762f43ee4184861ebb2016977b7

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Noland Wastewater Treatment Plant Hybrid / FAYEB

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID61204
Entity NameToday's Power, Inc.
Plant ID62682
Plant NameNoland Wastewater Treatment Plant Hybrid
Google MapMap
Bing MapMap
Plant StateAR
CountyWashington
Balancing Authority CodeSWPP
SectorCommercial Non-CHP
Generator IDFAYEB
Nameplate Capacity (MW)6
Net Summer Capacity (MW)6
Net Winter Capacity (MW)6
TechnologyBatteries
Energy Source CodeMWH
Prime Mover CodeBA
Operating Month7
Operating Year2019
Status(OP) Operating
Nameplate Energy Capacity (MWh)13.1
Latitude36.082301
Longitude-94.06715
Original text(OP) Operating
source_record_idOperating:21019

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:21019

Sources EV-8d76af5558a5710b30c3bd08
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 e931b1bc604e414c499b8e1b0906f60876897da4ef83111f1cdc8cfec19234d6

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel