POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Libby / 5

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)105 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-f1011fda5d6dd0a5f4cf9e4d
Net Summer Capacity (MW)105 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-f1011fda5d6dd0a5f4cf9e4d
Net Winter Capacity (MW)105 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-f1011fda5d6dd0a5f4cf9e4d
Detailed source fields
Original source fieldPublished value or condition
Entity ID19400
Entity NameUSACE Northwestern Division
Plant ID6172
Plant NameLibby
Google MapMap
Bing MapMap
Plant StateMT
CountyLincoln
Balancing Authority CodeBPAT
SectorElectric Utility
Generator ID5
Nameplate Capacity (MW)105
Net Summer Capacity (MW)105
Net Winter Capacity (MW)105
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month9
Operating Year1984
Status(OP) Operating
Latitude48.4098
Longitude-115.3143
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:6211

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:6205

Sources EV-8fbff23673d1695df66ac55a
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 26b0a08b92102b1abb6ccb698be3623dbac58dcebcad3e710b28fee1350a9252

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:6211

Sources EV-f1011fda5d6dd0a5f4cf9e4d
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 ad1fe22af9127c5446e147eaca1e5d6c8f95b8f43efc874161b97099a85931dd

Usage terms US government public domain

Source snapshots by date · USA · eia860

Libby / 5

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID19400
Utility NameUSACE Northwestern Division
Plant Code6172
Plant NameLibby
StateMT
CountyLincoln
Generator ID5
TechnologyConventional Hydroelectric
Prime MoverHY
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)105
Nameplate Power Factor0.95
Summer Capacity (MW)105
Winter Capacity (MW)105
Minimum Load (MW)105
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month9
Operating Year1984
Associated with Combined Heat and Power SystemN
Sector NameElectric Utility
Sector1
Topping or BottomingX
Energy Source 1WAT
Time from Cold Shutdown to Full Load10M
Multiple Fuels?N
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:6205

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:6205

Sources EV-8fbff23673d1695df66ac55a
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 26b0a08b92102b1abb6ccb698be3623dbac58dcebcad3e710b28fee1350a9252

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Libby / 5

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID19400
Entity NameUSACE Northwestern Division
Plant ID6172
Plant NameLibby
Google MapMap
Bing MapMap
Plant StateMT
CountyLincoln
Balancing Authority CodeBPAT
SectorElectric Utility
Generator ID5
Nameplate Capacity (MW)105
Net Summer Capacity (MW)105
Net Winter Capacity (MW)105
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month9
Operating Year1984
Status(OP) Operating
Latitude48.4098
Longitude-115.3143
Original text(OP) Operating
source_record_idOperating:6211

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:6211

Sources EV-f1011fda5d6dd0a5f4cf9e4d
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 ad1fe22af9127c5446e147eaca1e5d6c8f95b8f43efc874161b97099a85931dd

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel