POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

ABEC #2 dba West-Star Dairy / GEN1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)1 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-80f9aac0f933a943ceaf0bd3
Net Summer Capacity (MW)1 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-80f9aac0f933a943ceaf0bd3
Net Winter Capacity (MW)1 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-80f9aac0f933a943ceaf0bd3
Detailed source fields
Original source fieldPublished value or condition
Entity ID61105
Entity NameABEC #2 LLC
Plant ID61501
Plant NameABEC #2 dba West-Star Dairy
Google MapMap
Bing MapMap
Plant StateCA
CountyKern
Balancing Authority CodeCISO
SectorIPP Non-CHP
Generator IDGEN1
Nameplate Capacity (MW)1
Net Summer Capacity (MW)1
Net Winter Capacity (MW)1
TechnologyOther Waste Biomass
Energy Source CodeOBG
Prime Mover CodeIC
Operating Month2
Operating Year2018
Status(OP) Operating
Latitude35.472113
Longitude-119.4329
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:19683

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:19680

Sources EV-5d3f2fb352c7b3d7cffd35f6
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 d07bd52dc7d4a834e2a8d5c090f5892c061d5ab95c1a01a8a1ac1f35a2659785

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:19683

Sources EV-80f9aac0f933a943ceaf0bd3
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 0fcc0e3ba3495c70b74098c2130323572b43343813e1bd8d5fccf486bf5af353

Usage terms US government public domain

Source snapshots by date · USA · eia860

ABEC #2 dba West-Star Dairy / GEN1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID61105
Utility NameABEC #2 LLC
Plant Code61501
Plant NameABEC #2 dba West-Star Dairy
StateCA
CountyKern
Generator IDGEN1
TechnologyOther Waste Biomass
Prime MoverIC
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)1
Nameplate Power Factor0.9
Summer Capacity (MW)1
Winter Capacity (MW)1
Minimum Load (MW)0.8
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month2
Operating Year2018
Associated with Combined Heat and Power SystemN
Sector NameIPP Non-CHP
Sector2
Topping or BottomingX
Energy Source 1OBG
Startup Source 1OBG
Solid Fuel Gasification System?N
Carbon Capture Technology?N
Time from Cold Shutdown to Full Load1H
Pulverized Coal Technology?N
Multiple Fuels?N
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:19680

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:19680

Sources EV-5d3f2fb352c7b3d7cffd35f6
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 d07bd52dc7d4a834e2a8d5c090f5892c061d5ab95c1a01a8a1ac1f35a2659785

Usage terms US government public domain

Source snapshots by date · USA · eia860m

ABEC #2 dba West-Star Dairy / GEN1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID61105
Entity NameABEC #2 LLC
Plant ID61501
Plant NameABEC #2 dba West-Star Dairy
Google MapMap
Bing MapMap
Plant StateCA
CountyKern
Balancing Authority CodeCISO
SectorIPP Non-CHP
Generator IDGEN1
Nameplate Capacity (MW)1
Net Summer Capacity (MW)1
Net Winter Capacity (MW)1
TechnologyOther Waste Biomass
Energy Source CodeOBG
Prime Mover CodeIC
Operating Month2
Operating Year2018
Status(OP) Operating
Latitude35.472113
Longitude-119.4329
Original text(OP) Operating
source_record_idOperating:19683

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:19683

Sources EV-80f9aac0f933a943ceaf0bd3
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 0fcc0e3ba3495c70b74098c2130323572b43343813e1bd8d5fccf486bf5af353

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel