POWER & FACILITY EVIDENCE
Power and Facility Evidence Database Review power assets, contract observations, facility specifications and relationships from public sources.
Global Facilities and Power Map Korea Site and Power Map Korea Data Center Database This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 3items · current page 1–3 · Source records, not unique facilities.
Power assets and projects · USA · eia860m Comanche Peak / 1 Generator · Operations
Metric or condition Source value Basis, scope and stage Nameplate Capacity (MW) 1215 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-c8432d6c54a3d309a75cd444 Net Summer Capacity (MW) 1205 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-c8432d6c54a3d309a75cd444 Net Winter Capacity (MW) 1235 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-c8432d6c54a3d309a75cd444
Detailed source fields Original source field Published value or condition Entity ID 55983 Entity Name Luminant Generation Company LLC Plant ID 6145 Plant Name Comanche Peak Google Map Map Bing Map Map Plant State TX County Somervell Balancing Authority Code ERCO Sector IPP Non-CHP Generator ID 1 Nameplate Capacity (MW) 1215 Net Summer Capacity (MW) 1205 Net Winter Capacity (MW) 1235 Technology Nuclear Energy Source Code NUC Prime Mover Code ST Operating Month 8 Operating Year 1990 Status (OP) Operating Latitude 32.298365 Longitude -97.78552 Original text (OP) Operating Coordinate accuracy source_precision_not_independently_surveyed source_record_id Operating:6137
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Operable:6131
Sources EV-a6a314e2a97207c4abd66b20 Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 de3287c6da981e41c6231123ca3bdf10960ce0dec79ff50100fba935b02f2454 Usage terms US government public domain
eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:6137
Sources EV-c8432d6c54a3d309a75cd444 Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 7af6a85a81c739e2b6565f20bd4e4102d981aa3a79410af8acc3fb09f5aac465 Usage terms US government public domain
Observations for this power asset View on the global map Source snapshots by date · USA · eia860 Comanche Peak / 1 Generator · Operations
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Utility ID 55983 Utility Name Luminant Generation Company LLC Plant Code 6145 Plant Name Comanche Peak State TX County Somervell Generator ID 1 Technology Nuclear Prime Mover ST Ownership W Duct Burners X Can Bypass Heat Recovery Steam Generator? X Nameplate Capacity (MW) 1215 Nameplate Power Factor 0.9 Summer Capacity (MW) 1205 Winter Capacity (MW) 1235 Minimum Load (MW) 1112 Uprate or Derate Completed During Year N Status OP Synchronized to Transmission Grid X Operating Month 8 Operating Year 1990 Associated with Combined Heat and Power System N Sector Name IPP Non-CHP Sector 2 Topping or Bottoming X Energy Source 1 NUC Solid Fuel Gasification System? N Carbon Capture Technology? N Time from Cold Shutdown to Full Load OVER Multiple Fuels? N Original text OP source_record_id 3_1_Generator_Y2025.xlsx#Operable:6131
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Operable:6131
Sources EV-a6a314e2a97207c4abd66b20 Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 de3287c6da981e41c6231123ca3bdf10960ce0dec79ff50100fba935b02f2454 Usage terms US government public domain
Observations for this power asset Source snapshots by date · USA · eia860m Comanche Peak / 1 Generator · Operations
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Entity ID 55983 Entity Name Luminant Generation Company LLC Plant ID 6145 Plant Name Comanche Peak Google Map Map Bing Map Map Plant State TX County Somervell Balancing Authority Code ERCO Sector IPP Non-CHP Generator ID 1 Nameplate Capacity (MW) 1215 Net Summer Capacity (MW) 1205 Net Winter Capacity (MW) 1235 Technology Nuclear Energy Source Code NUC Prime Mover Code ST Operating Month 8 Operating Year 1990 Status (OP) Operating Latitude 32.298365 Longitude -97.78552 Original text (OP) Operating source_record_id Operating:6137
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:6137
Sources EV-c8432d6c54a3d309a75cd444 Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 7af6a85a81c739e2b6565f20bd4e4102d981aa3a79410af8acc3fb09f5aac465 Usage terms US government public domain
Observations for this power asset