POWER & FACILITY EVIDENCE
Power and Facility Evidence Database Review power assets, contract observations, facility specifications and relationships from public sources.
Global Facilities and Power Map Korea Site and Power Map Korea Data Center Database This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 3items · current page 1–3 · Source records, not unique facilities.
Power assets and projects · USA · eia860m CES Sterling LLC / 1 Generator · Operations
Metric or condition Source value Basis, scope and stage Nameplate Capacity (MW) 2 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-008aa8be5d42a747e8211466 Net Summer Capacity (MW) 2 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-008aa8be5d42a747e8211466 Net Winter Capacity (MW) 2 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-008aa8be5d42a747e8211466 DC Net Capacity (MW) 2.4 MWdc Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-008aa8be5d42a747e8211466
Detailed source fields Original source field Published value or condition Entity ID 59139 Entity Name SunEdison LLC Plant ID 58387 Plant Name CES Sterling LLC Google Map Map Bing Map Map Plant State MA County Worcester Balancing Authority Code ISNE Sector IPP Non-CHP Generator ID 1 Nameplate Capacity (MW) 2 Net Summer Capacity (MW) 2 Net Winter Capacity (MW) 2 Technology Solar Photovoltaic Energy Source Code SUN Prime Mover Code PV Operating Month 2 Operating Year 2013 Status (OP) Operating DC Net Capacity (MW) 2.4 Latitude 42.441944 Longitude -71.72222 Original text (OP) Operating Coordinate accuracy source_precision_not_independently_surveyed source_record_id Operating:16095
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Operable:16097
Sources EV-1fb8a74c3b78ae50df6804de Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 bd93ae8d246d05b82e69e3d10412610e9faf7f9ada0116098dccd5e5e2af94b9 Usage terms US government public domain
eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:16095
Sources EV-008aa8be5d42a747e8211466 Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 da4eb03d7a77b227940ac504ac735f38d4be5a51415b1c3215e03b70e2aa54d8 Usage terms US government public domain
Observations for this power asset View on the global map Source snapshots by date · USA · eia860m CES Sterling LLC / 1 Generator · Operations
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Entity ID 59139 Entity Name SunEdison LLC Plant ID 58387 Plant Name CES Sterling LLC Google Map Map Bing Map Map Plant State MA County Worcester Balancing Authority Code ISNE Sector IPP Non-CHP Generator ID 1 Nameplate Capacity (MW) 2 Net Summer Capacity (MW) 2 Net Winter Capacity (MW) 2 Technology Solar Photovoltaic Energy Source Code SUN Prime Mover Code PV Operating Month 2 Operating Year 2013 Status (OP) Operating DC Net Capacity (MW) 2.4 Latitude 42.441944 Longitude -71.72222 Original text (OP) Operating source_record_id Operating:16095
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:16095
Sources EV-008aa8be5d42a747e8211466 Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 da4eb03d7a77b227940ac504ac735f38d4be5a51415b1c3215e03b70e2aa54d8 Usage terms US government public domain
Observations for this power asset Source snapshots by date · USA · eia860 CES Sterling LLC / 1 Generator · Operations
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Utility ID 59139 Utility Name SunEdison LLC Plant Code 58387 Plant Name CES Sterling LLC State MA County Worcester Generator ID 1 Technology Solar Photovoltaic Prime Mover PV Ownership S Duct Burners X Can Bypass Heat Recovery Steam Generator? X Nameplate Capacity (MW) 2 Summer Capacity (MW) 2 Winter Capacity (MW) 2 Uprate or Derate Completed During Year N Status OP Synchronized to Transmission Grid X Operating Month 2 Operating Year 2013 Associated with Combined Heat and Power System N Sector Name IPP Non-CHP Sector 2 Topping or Bottoming X Energy Source 1 SUN Solid Fuel Gasification System? N Original text OP source_record_id 3_1_Generator_Y2025.xlsx#Operable:16097
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Operable:16097
Sources EV-1fb8a74c3b78ae50df6804de Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 bd93ae8d246d05b82e69e3d10412610e9faf7f9ada0116098dccd5e5e2af94b9 Usage terms US government public domain
Observations for this power asset