POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Gastonia Prime Power Park / 1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)2.3 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-9a4792e56f329f6517f99a33
Net Summer Capacity (MW)2 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-9a4792e56f329f6517f99a33
Net Winter Capacity (MW)2 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-9a4792e56f329f6517f99a33
Detailed source fields
Original source fieldPublished value or condition
Entity ID13630
Entity NameNorth Carolina Mun Power Agny #1
Plant ID56954
Plant NameGastonia Prime Power Park
Google MapMap
Bing MapMap
Plant StateNC
CountyGaston
Balancing Authority CodeDUK
SectorElectric Utility
Generator ID1
Nameplate Capacity (MW)2.3
Net Summer Capacity (MW)2
Net Winter Capacity (MW)2
TechnologyPetroleum Liquids
Energy Source CodeDFO
Prime Mover CodeIC
Operating Month6
Operating Year2008
Status(OP) Operating
Latitude35.3017
Longitude-81.2092
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:14191

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:14187

Sources EV-d732c8469c414b697e02631d
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 cf71d446abdca7edd16f57601ce885bc7318975709b0ae4e6a18eb816d081465

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:14191

Sources EV-9a4792e56f329f6517f99a33
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 1f86c4c29146d164503b88ab37574c9101aa6120f1ac7028d0c53a5934f09fa3

Usage terms US government public domain

Source snapshots by date · USA · eia860

Gastonia Prime Power Park / 1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID13630
Utility NameNorth Carolina Mun Power Agny #1
Plant Code56954
Plant NameGastonia Prime Power Park
StateNC
CountyGaston
Generator ID1
TechnologyPetroleum Liquids
Prime MoverIC
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)2.3
Nameplate Power Factor0.8
Summer Capacity (MW)2
Winter Capacity (MW)2
Minimum Load (MW)0.1
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month6
Operating Year2008
Associated with Combined Heat and Power SystemN
Sector NameElectric Utility
Sector1
Topping or BottomingX
Energy Source 1DFO
Solid Fuel Gasification System?N
Carbon Capture Technology?N
Time from Cold Shutdown to Full Load10M
Multiple Fuels?N
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:14187

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:14187

Sources EV-d732c8469c414b697e02631d
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 cf71d446abdca7edd16f57601ce885bc7318975709b0ae4e6a18eb816d081465

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Gastonia Prime Power Park / 1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID13630
Entity NameNorth Carolina Mun Power Agny #1
Plant ID56954
Plant NameGastonia Prime Power Park
Google MapMap
Bing MapMap
Plant StateNC
CountyGaston
Balancing Authority CodeDUK
SectorElectric Utility
Generator ID1
Nameplate Capacity (MW)2.3
Net Summer Capacity (MW)2
Net Winter Capacity (MW)2
TechnologyPetroleum Liquids
Energy Source CodeDFO
Prime Mover CodeIC
Operating Month6
Operating Year2008
Status(OP) Operating
Latitude35.3017
Longitude-81.2092
Original text(OP) Operating
source_record_idOperating:14191

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:14191

Sources EV-9a4792e56f329f6517f99a33
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 1f86c4c29146d164503b88ab37574c9101aa6120f1ac7028d0c53a5934f09fa3

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel