POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Lange Generating Station / IC06

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)16.6 MWOriginal source column definition · Generator · (V) Under construction, more than 50 percent complete
As-of date 2026-08
Sources EV-77d020df90e36d9bb20f4569
Net Summer Capacity (MW)16.3 MWOriginal source column definition · Generator · (V) Under construction, more than 50 percent complete
As-of date 2026-08
Sources EV-77d020df90e36d9bb20f4569
Net Winter Capacity (MW)16.3 MWOriginal source column definition · Generator · (V) Under construction, more than 50 percent complete
As-of date 2026-08
Sources EV-77d020df90e36d9bb20f4569
Detailed source fields
Original source fieldPublished value or condition
Entity ID19545
Entity NameBlack Hills Power, Inc.
Plant ID55478
Plant NameLange Generating Station
Google MapMap
Bing MapMap
Plant StateSD
CountyPennington
Balancing Authority CodeWACM
SectorElectric Utility
Generator IDIC06
Nameplate Capacity (MW)16.6
Net Summer Capacity (MW)16.3
Net Winter Capacity (MW)16.3
TechnologyNatural Gas Internal Combustion Engine
Energy Source CodeNG
Prime Mover CodeIC
Planned Operation Month12
Planned Operation Year2026
Status(V) Under construction, more than 50 percent complete
Latitude44.1218
Longitude-103.2641
Original text(V) Under construction, more than 50 percent complete
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idPlanned:440

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:180

Sources EV-b5558c179a18a7c16bff36eb
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 a3da3cb7ffb178fa3cf16d82dd0438c56cb024c7a47e4c2f29289150d1240c4e

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:440

Sources EV-77d020df90e36d9bb20f4569
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 a27257b29295938bea85f68b679aa46670a172d588afa15b4349a59f89492067

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Lange Generating Station / IC06

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID19545
Entity NameBlack Hills Power, Inc.
Plant ID55478
Plant NameLange Generating Station
Google MapMap
Bing MapMap
Plant StateSD
CountyPennington
Balancing Authority CodeWACM
SectorElectric Utility
Generator IDIC06
Nameplate Capacity (MW)16.6
Net Summer Capacity (MW)16.3
Net Winter Capacity (MW)16.3
TechnologyNatural Gas Internal Combustion Engine
Energy Source CodeNG
Prime Mover CodeIC
Planned Operation Month12
Planned Operation Year2026
Status(V) Under construction, more than 50 percent complete
Latitude44.1218
Longitude-103.2641
Original text(V) Under construction, more than 50 percent complete
source_record_idPlanned:440

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Planned:440

Sources EV-77d020df90e36d9bb20f4569
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 a27257b29295938bea85f68b679aa46670a172d588afa15b4349a59f89492067

Usage terms US government public domain

Source snapshots by date · USA · eia860

Lange Generating Station / IC06

Generator · Plan

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID19545
Utility NameBlack Hills Power, Inc.
Plant Code55478
Plant NameLange Generating Station
StateSD
CountyPennington
Generator IDIC06
TechnologyNatural Gas Internal Combustion Engine
Prime MoverIC
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)16.6
Nameplate Power Factor0.85
Summer Capacity (MW)16.3
Winter Capacity (MW)16.3
StatusT
Effective Month9
Effective Year2026
Current Month12
Current Year2026
Associated with Combined Heat and Power SystemN
Sector NameElectric Utility
Sector1
Previously CanceledN
Energy Source 1NG
Energy Source 2DFO
Multiple Fuels?Y
Switch Between Oil and Natural Gas?Y
Cofire Fuels?N
Original textT
source_record_id3_1_Generator_Y2025.xlsx#Proposed:180

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Proposed:180

Sources EV-b5558c179a18a7c16bff36eb
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 a3da3cb7ffb178fa3cf16d82dd0438c56cb024c7a47e4c2f29289150d1240c4e

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel