Power assets and projects · USA · eia860m
Red Hawk / CT9
Generator · Plan
Metric or condition
Source value
Basis, scope and stage
Nameplate Capacity (MW)
49 MW
Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-c29b55b50263c3b8ebdf0477
Net Summer Capacity (MW)
45 MW
Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-c29b55b50263c3b8ebdf0477
Net Winter Capacity (MW)
49 MW
Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-c29b55b50263c3b8ebdf0477
Detailed source fields
Original source field
Published value or condition
Entity ID
803
Entity Name
Arizona Public Service Co
Plant ID
55455
Plant Name
Red Hawk
Google Map
Map
Bing Map
Map
Plant State
AZ
County
Maricopa
Balancing Authority Code
SRP
Sector
Electric Utility
Generator ID
CT9
Nameplate Capacity (MW)
49
Net Summer Capacity (MW)
45
Net Winter Capacity (MW)
49
Technology
Natural Gas Fired Combustion Turbine
Energy Source Code
NG
Prime Mover Code
GT
Planned Operation Month
10
Planned Operation Year
2027
Status
(U) Under construction, less than or equal to 50 percent complete
Latitude
33.334562
Longitude
-112.8406
Original text
(U) Under construction, less than or equal to 50 percent complete