POWER & FACILITY EVIDENCE
Power and Facility Evidence Database Review power assets, contract observations, facility specifications and relationships from public sources.
Global Facilities and Power Map Korea Site and Power Map Korea Data Center Database This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 3items · current page 1–3 · Source records, not unique facilities.
Power assets and projects · USA · eia860m I 95 Landfill Phase II / UNT2 Generator · Operations
Metric or condition Source value Basis, scope and stage Nameplate Capacity (MW) 0.8 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-252e0ddb1dd9db3d36466378 Net Summer Capacity (MW) 0.8 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-252e0ddb1dd9db3d36466378 Net Winter Capacity (MW) 0.8 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-252e0ddb1dd9db3d36466378
Detailed source fields Original source field Published value or condition Entity ID 57249 Entity Name NextEra Renewable Fuels, LLC Plant ID 54723 Plant Name I 95 Landfill Phase II Google Map Map Bing Map Map Plant State VA County Fairfax Balancing Authority Code PJM Sector IPP Non-CHP Generator ID UNT2 Nameplate Capacity (MW) 0.8 Net Summer Capacity (MW) 0.8 Net Winter Capacity (MW) 0.8 Technology Landfill Gas Energy Source Code LFG Prime Mover Code IC Operating Month 3 Operating Year 1993 Status (OP) Operating Latitude 38.6892 Longitude -77.2375 Original text (OP) Operating Coordinate accuracy source_precision_not_independently_surveyed source_record_id Operating:10842
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Operable:10840
Sources EV-f066eb8ce3d0c6dae0acad38 Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 7f70a1f663ca178e8a4873ed3fb619ab7a0320969d24b407c34f2173d1216fe5 Usage terms US government public domain
eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:10842
Sources EV-252e0ddb1dd9db3d36466378 Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 3101972a4f58b0662472b956cd2e55507fc4b4cf95bf19309e3530c6464ee272 Usage terms US government public domain
Observations for this power asset View on the global map Source snapshots by date · USA · eia860 I 95 Landfill Phase II / UNT2 Generator · Operations
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Utility ID 57249 Utility Name NextEra Renewable Fuels, LLC Plant Code 54723 Plant Name I 95 Landfill Phase II State VA County Fairfax Generator ID UNT2 Technology Landfill Gas Prime Mover IC Ownership S Duct Burners X Can Bypass Heat Recovery Steam Generator? X Nameplate Capacity (MW) 0.8 Nameplate Power Factor 0.95 Summer Capacity (MW) 0.8 Winter Capacity (MW) 0.8 Minimum Load (MW) 0.3 Uprate or Derate Completed During Year N Status OP Synchronized to Transmission Grid X Operating Month 3 Operating Year 1993 Associated with Combined Heat and Power System N Sector Name IPP Non-CHP Sector 2 Topping or Bottoming X Energy Source 1 LFG Solid Fuel Gasification System? N Carbon Capture Technology? N Time from Cold Shutdown to Full Load 10M Multiple Fuels? N Original text OP source_record_id 3_1_Generator_Y2025.xlsx#Operable:10840
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Operable:10840
Sources EV-f066eb8ce3d0c6dae0acad38 Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 7f70a1f663ca178e8a4873ed3fb619ab7a0320969d24b407c34f2173d1216fe5 Usage terms US government public domain
Observations for this power asset Source snapshots by date · USA · eia860m I 95 Landfill Phase II / UNT2 Generator · Operations
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Entity ID 57249 Entity Name NextEra Renewable Fuels, LLC Plant ID 54723 Plant Name I 95 Landfill Phase II Google Map Map Bing Map Map Plant State VA County Fairfax Balancing Authority Code PJM Sector IPP Non-CHP Generator ID UNT2 Nameplate Capacity (MW) 0.8 Net Summer Capacity (MW) 0.8 Net Winter Capacity (MW) 0.8 Technology Landfill Gas Energy Source Code LFG Prime Mover Code IC Operating Month 3 Operating Year 1993 Status (OP) Operating Latitude 38.6892 Longitude -77.2375 Original text (OP) Operating source_record_id Operating:10842
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:10842
Sources EV-252e0ddb1dd9db3d36466378 Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 3101972a4f58b0662472b956cd2e55507fc4b4cf95bf19309e3530c6464ee272 Usage terms US government public domain
Observations for this power asset