Power assets and projects · USA · eia860m

Yuba City Cogen Partners / GEN1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)49.9 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-3b590e59505d1a86962aef1a
Net Summer Capacity (MW)49.9 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-3b590e59505d1a86962aef1a
Net Winter Capacity (MW)49.9 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-3b590e59505d1a86962aef1a
Detailed source fields
Original source fieldPublished value or condition
Entity ID20323
Entity NameWellhead Services, Inc
Plant ID52186
Plant NameYuba City Cogen Partners
Google MapMap
Bing MapMap
Plant StateCA
CountySutter
Balancing Authority CodeCISO
SectorIPP CHP
Generator IDGEN1
Nameplate Capacity (MW)49.9
Net Summer Capacity (MW)49.9
Net Winter Capacity (MW)49.9
TechnologyNatural Gas Fired Combustion Turbine
Energy Source CodeNG
Prime Mover CodeGT
Operating Month12
Operating Year1990
Status(OP) Operating
Latitude39.13667
Longitude-121.6398
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:10164

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:10161

Sources EV-aeaa83cdd6f4d5b7513b4f91
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 64a3fc9ad86194a5bd62429917f305862ad24cb4e4a05ab5809c5a82b893623f

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:10164

Sources EV-3b590e59505d1a86962aef1a
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 00e39bdce025974cae42d7579f2c5184720e2a4f5ffa376eceb39240f90c264e

Usage terms US government public domain

Source snapshots by date · USA · eia860

Yuba City Cogen Partners / GEN1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID20323
Utility NameWellhead Services, Inc
Plant Code52186
Plant NameYuba City Cogen Partners
StateCA
CountySutter
Generator IDGEN1
TechnologyNatural Gas Fired Combustion Turbine
Prime MoverGT
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)49.9
Nameplate Power Factor0.9
Summer Capacity (MW)49.9
Winter Capacity (MW)49.9
Minimum Load (MW)42
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month12
Operating Year1990
Associated with Combined Heat and Power SystemY
Sector NameIPP CHP
Sector3
Topping or BottomingT
Energy Source 1NG
Solid Fuel Gasification System?N
Carbon Capture Technology?N
Time from Cold Shutdown to Full Load12H
Multiple Fuels?N
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:10161

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:10161

Sources EV-aeaa83cdd6f4d5b7513b4f91
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 64a3fc9ad86194a5bd62429917f305862ad24cb4e4a05ab5809c5a82b893623f

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Yuba City Cogen Partners / GEN1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID20323
Entity NameWellhead Services, Inc
Plant ID52186
Plant NameYuba City Cogen Partners
Google MapMap
Bing MapMap
Plant StateCA
CountySutter
Balancing Authority CodeCISO
SectorIPP CHP
Generator IDGEN1
Nameplate Capacity (MW)49.9
Net Summer Capacity (MW)49.9
Net Winter Capacity (MW)49.9
TechnologyNatural Gas Fired Combustion Turbine
Energy Source CodeNG
Prime Mover CodeGT
Operating Month12
Operating Year1990
Status(OP) Operating
Latitude39.13667
Longitude-121.6398
Original text(OP) Operating
source_record_idOperating:10164

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:10164

Sources EV-3b590e59505d1a86962aef1a
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 00e39bdce025974cae42d7579f2c5184720e2a4f5ffa376eceb39240f90c264e

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel