POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Lee County Solid Waste Energy / GEN2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)20 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-7a85bf14bd9526de22b1fd7b
Net Summer Capacity (MW)16 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-7a85bf14bd9526de22b1fd7b
Net Winter Capacity (MW)16 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-7a85bf14bd9526de22b1fd7b
Detailed source fields
Original source fieldPublished value or condition
Entity ID10875
Entity NameLee County Board-Commissioners
Plant ID52010
Plant NameLee County Solid Waste Energy
Google MapMap
Bing MapMap
Plant StateFL
CountyLee
Balancing Authority CodeFPL
SectorIPP Non-CHP
Generator IDGEN2
Nameplate Capacity (MW)20
Net Summer Capacity (MW)16
Net Winter Capacity (MW)16
TechnologyMunicipal Solid Waste
Energy Source CodeMSW
Prime Mover CodeST
Operating Month8
Operating Year2007
Planned Retirement Month8
Planned Retirement Year2072
Status(OP) Operating
Latitude26.631549
Longitude-81.76066
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:9969

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:9965

Sources EV-740b9d862691655092a270f2
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 fad3cdaa4cdc76eea8465ca7addfa8083b74a874bdf340b4d6b97f0287db3a3f

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:9969

Sources EV-7a85bf14bd9526de22b1fd7b
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 2b201767e87180cfa84c3337c5ae9f5eb1aeb66d475581942795d51d3dee7678

Usage terms US government public domain

Source snapshots by date · USA · eia860

Lee County Solid Waste Energy / GEN2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID10875
Utility NameLee County Board-Commissioners
Plant Code52010
Plant NameLee County Solid Waste Energy
StateFL
CountyLee
Generator IDGEN2
TechnologyMunicipal Solid Waste
Prime MoverST
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)20
Nameplate Power Factor0.85
Summer Capacity (MW)16
Winter Capacity (MW)16
Minimum Load (MW)10
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month8
Operating Year2007
Planned Retirement Month8
Planned Retirement Year2072
Associated with Combined Heat and Power SystemN
Sector NameIPP Non-CHP
Sector2
Topping or BottomingX
Energy Source 1MSW
Startup Source 1PG
Solid Fuel Gasification System?N
Carbon Capture Technology?N
Time from Cold Shutdown to Full Load12H
Multiple Fuels?N
Cofire Fuels?N
Switch Between Oil and Natural Gas?N
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:9965

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:9965

Sources EV-740b9d862691655092a270f2
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 fad3cdaa4cdc76eea8465ca7addfa8083b74a874bdf340b4d6b97f0287db3a3f

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Lee County Solid Waste Energy / GEN2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID10875
Entity NameLee County Board-Commissioners
Plant ID52010
Plant NameLee County Solid Waste Energy
Google MapMap
Bing MapMap
Plant StateFL
CountyLee
Balancing Authority CodeFPL
SectorIPP Non-CHP
Generator IDGEN2
Nameplate Capacity (MW)20
Net Summer Capacity (MW)16
Net Winter Capacity (MW)16
TechnologyMunicipal Solid Waste
Energy Source CodeMSW
Prime Mover CodeST
Operating Month8
Operating Year2007
Planned Retirement Month8
Planned Retirement Year2072
Status(OP) Operating
Latitude26.631549
Longitude-81.76066
Original text(OP) Operating
source_record_idOperating:9969

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:9969

Sources EV-7a85bf14bd9526de22b1fd7b
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 2b201767e87180cfa84c3337c5ae9f5eb1aeb66d475581942795d51d3dee7678

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel