Power assets and projects · USA · eia860m

Penacook Upper Falls Hydro / 1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)3.4 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-399589de9826f92d944c77b0
Net Summer Capacity (MW)3.4 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-399589de9826f92d944c77b0
Net Winter Capacity (MW)3.4 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-399589de9826f92d944c77b0
Detailed source fields
Original source fieldPublished value or condition
Entity ID24793
Entity NameBriar-Hydro Associates
Plant ID50414
Plant NamePenacook Upper Falls Hydro
Google MapMap
Bing MapMap
Plant StateNH
CountyMerrimack
Balancing Authority CodeISNE
SectorIPP Non-CHP
Generator ID1
Nameplate Capacity (MW)3.4
Net Summer Capacity (MW)3.4
Net Winter Capacity (MW)3.4
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month12
Operating Year1986
Status(OP) Operating
Latitude43.283208
Longitude-71.60083
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:9454

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:9450

Sources EV-07ccd762aecb237ad4485056
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 76bfa3800631caf2156139ec3310d3bf32432b5fc59d5f32461598afd2b61bbf

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:9454

Sources EV-399589de9826f92d944c77b0
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 afa86d6f7f19573595b6179638cde399c55b780dcd87a652192cdce0391061fe

Usage terms US government public domain

Source snapshots by date · USA · eia860

Penacook Upper Falls Hydro / 1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID24793
Utility NameBriar-Hydro Associates
Plant Code50414
Plant NamePenacook Upper Falls Hydro
StateNH
CountyMerrimack
Generator ID1
TechnologyConventional Hydroelectric
Prime MoverHY
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)3.4
Nameplate Power Factor0.9
Summer Capacity (MW)3.4
Winter Capacity (MW)3.4
Minimum Load (MW)0.1
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month12
Operating Year1986
Associated with Combined Heat and Power SystemN
Sector NameIPP Non-CHP
Sector2
Topping or BottomingX
Energy Source 1WAT
Solid Fuel Gasification System?N
Time from Cold Shutdown to Full Load1H
Multiple Fuels?N
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:9450

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:9450

Sources EV-07ccd762aecb237ad4485056
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 76bfa3800631caf2156139ec3310d3bf32432b5fc59d5f32461598afd2b61bbf

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Penacook Upper Falls Hydro / 1

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID24793
Entity NameBriar-Hydro Associates
Plant ID50414
Plant NamePenacook Upper Falls Hydro
Google MapMap
Bing MapMap
Plant StateNH
CountyMerrimack
Balancing Authority CodeISNE
SectorIPP Non-CHP
Generator ID1
Nameplate Capacity (MW)3.4
Net Summer Capacity (MW)3.4
Net Winter Capacity (MW)3.4
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month12
Operating Year1986
Status(OP) Operating
Latitude43.283208
Longitude-71.60083
Original text(OP) Operating
source_record_idOperating:9454

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:9454

Sources EV-399589de9826f92d944c77b0
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 afa86d6f7f19573595b6179638cde399c55b780dcd87a652192cdce0391061fe

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel