POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Passaic Valley Water Commission / GEN1

Generator · Out of service

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)0.6 MWOriginal source column definition · Generator · (OS) Out of service and NOT expected to return to service in next calendar year
As-of date 2026-08
Sources EV-de8476ad5dd2b70a08ee80ee
Net Summer Capacity (MW)0.6 MWOriginal source column definition · Generator · (OS) Out of service and NOT expected to return to service in next calendar year
As-of date 2026-08
Sources EV-de8476ad5dd2b70a08ee80ee
Net Winter Capacity (MW)0.6 MWOriginal source column definition · Generator · (OS) Out of service and NOT expected to return to service in next calendar year
As-of date 2026-08
Sources EV-de8476ad5dd2b70a08ee80ee
Detailed source fields
Original source fieldPublished value or condition
Entity ID14539
Entity NamePassaic Valley Water Comm
Plant ID50311
Plant NamePassaic Valley Water Commission
Google MapMap
Bing MapMap
Plant StateNJ
CountyPassaic
Balancing Authority CodePJM
SectorIPP Non-CHP
Generator IDGEN1
Nameplate Capacity (MW)0.6
Net Summer Capacity (MW)0.6
Net Winter Capacity (MW)0.6
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month1
Operating Year1935
Status(OS) Out of service and NOT expected to return to service in next calendar year
Other Modification Year2036
Other Modification Month6
Latitude40.883345
Longitude-74.22999
Original text(OS) Out of service and NOT expected to return to service in next calendar year
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:9316

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:9314

Sources EV-521beaefc64d53f12bf76c0e
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 2664a8f0b0491b3a09e3f4c1737c5908e440c27dc920994adbe84827946ed016

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:9316

Sources EV-de8476ad5dd2b70a08ee80ee
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 e0974e24530dd9c563c3b478d012c741de0256d4e6c7f961c264872b2250cf1f

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Passaic Valley Water Commission / GEN1

Generator · Out of service

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID14539
Entity NamePassaic Valley Water Comm
Plant ID50311
Plant NamePassaic Valley Water Commission
Google MapMap
Bing MapMap
Plant StateNJ
CountyPassaic
Balancing Authority CodePJM
SectorIPP Non-CHP
Generator IDGEN1
Nameplate Capacity (MW)0.6
Net Summer Capacity (MW)0.6
Net Winter Capacity (MW)0.6
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month1
Operating Year1935
Status(OS) Out of service and NOT expected to return to service in next calendar year
Other Modification Year2036
Other Modification Month6
Latitude40.883345
Longitude-74.22999
Original text(OS) Out of service and NOT expected to return to service in next calendar year
source_record_idOperating:9316

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:9316

Sources EV-de8476ad5dd2b70a08ee80ee
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 e0974e24530dd9c563c3b478d012c741de0256d4e6c7f961c264872b2250cf1f

Usage terms US government public domain

Source snapshots by date · USA · eia860

Passaic Valley Water Commission / GEN1

Generator · Out of service

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID14539
Utility NamePassaic Valley Water Comm
Plant Code50311
Plant NamePassaic Valley Water Commission
StateNJ
CountyPassaic
Generator IDGEN1
TechnologyConventional Hydroelectric
Prime MoverHY
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)0.6
Nameplate Power Factor0.89
Summer Capacity (MW)0.6
Winter Capacity (MW)0.6
Minimum Load (MW)0.3
Uprate or Derate Completed During YearN
StatusOS
Synchronized to Transmission GridX
Operating Month1
Operating Year1935
Associated with Combined Heat and Power SystemN
Sector NameIPP Non-CHP
Sector2
Topping or BottomingX
Energy Source 1WAT
Solid Fuel Gasification System?N
Time from Cold Shutdown to Full LoadOVER
Other Planned Modifications?Y
Other Modifications Month6
Other Modifications Year2036
Original textOS
source_record_id3_1_Generator_Y2025.xlsx#Operable:9314

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:9314

Sources EV-521beaefc64d53f12bf76c0e
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 2664a8f0b0491b3a09e3f4c1737c5908e440c27dc920994adbe84827946ed016

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel