Review power assets, contract observations, facility specifications and relationships from public sources.
This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 3items · current page 1–3 · Source records, not unique facilities.
Power assets and projects · USA · eia860m
Chesterfield / CERC3
Generator · Plan
Metric or condition
Source value
Basis, scope and stage
Nameplate Capacity (MW)
250 MW
Original source column definition · Generator · (L) Regulatory approvals pending. Not under construction As-of date 2026-08 Sources EV-8462ae7978e4f27fe4e720b1
Net Summer Capacity (MW)
233.9 MW
Original source column definition · Generator · (L) Regulatory approvals pending. Not under construction As-of date 2026-08 Sources EV-8462ae7978e4f27fe4e720b1
Net Winter Capacity (MW)
243.8 MW
Original source column definition · Generator · (L) Regulatory approvals pending. Not under construction As-of date 2026-08 Sources EV-8462ae7978e4f27fe4e720b1
Detailed source fields
Original source field
Published value or condition
Entity ID
19876
Entity Name
Virginia Electric & Power Co
Plant ID
3797
Plant Name
Chesterfield
Google Map
Map
Bing Map
Map
Plant State
VA
County
Chesterfield
Balancing Authority Code
PJM
Sector
Electric Utility
Generator ID
CERC3
Nameplate Capacity (MW)
250
Net Summer Capacity (MW)
233.9
Net Winter Capacity (MW)
243.8
Technology
Natural Gas Fired Combustion Turbine
Energy Source Code
NG
Prime Mover Code
GT
Planned Operation Month
6
Planned Operation Year
2029
Status
(L) Regulatory approvals pending. Not under construction
Latitude
37.3822
Longitude
-77.3833
Original text
(L) Regulatory approvals pending. Not under construction