Global Facilities and Power Map Korea Site and Power Map Korea Data Center Database This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.
Current filters 3items · current page 1–3 · Source records, not unique facilities.
Power assets and projects · USA · eia860m Buck Hydro / 1 Generator · Operations
Metric or condition Source value Basis, scope and stage Nameplate Capacity (MW) 2.8 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-67b39c47a77961a82bc4b706 Net Summer Capacity (MW) 3 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-67b39c47a77961a82bc4b706 Net Winter Capacity (MW) 5.3 MW Original source column definition · Generator · (OP) Operating As-of date 2026-08 Sources EV-67b39c47a77961a82bc4b706
Detailed source fields Original source field Published value or condition Entity ID 733 Entity Name Appalachian Power Co Plant ID 3772 Plant Name Buck Hydro Google Map Map Bing Map Map Plant State VA County Carroll Balancing Authority Code PJM Sector Electric Utility Generator ID 1 Nameplate Capacity (MW) 2.8 Net Summer Capacity (MW) 3 Net Winter Capacity (MW) 5.3 Technology Conventional Hydroelectric Energy Source Code WAT Prime Mover Code HY Operating Month 1 Operating Year 1912 Status (OP) Operating Latitude 36.808229 Longitude -80.93871 Original text (OP) Operating Coordinate accuracy source_precision_not_independently_surveyed source_record_id Operating:5225
Parent facility or plant record
Coordinates locate the plant, including when this record describes one generator.
Location: Plant location · not an individual generator location
Sources, reference dates and retrieval dates 2items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Operable:5220
Sources EV-df9ff0a2b8b69bfad52b5b6a Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 a61700fff80bdb64917a62af28a7c823579d0c5cb20796f233eb64c7b92565ce Usage terms US government public domain
eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:5225
Sources EV-67b39c47a77961a82bc4b706 Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 2c1eb65a61776ec250475888f0b51fe873a18c37870e38db460ea129f42d1c00 Usage terms US government public domain
Observations for this power asset View on the global map Source snapshots by date · USA · eia860 Buck Hydro / 1 Generator · Operations
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Utility ID 733 Utility Name Appalachian Power Co Plant Code 3772 Plant Name Buck Hydro State VA County Carroll Generator ID 1 Technology Conventional Hydroelectric Prime Mover HY Ownership S Duct Burners X Can Bypass Heat Recovery Steam Generator? X Nameplate Capacity (MW) 2.8 Nameplate Power Factor 0.9 Summer Capacity (MW) 3 Winter Capacity (MW) 5.3 Minimum Load (MW) 0.2 Uprate or Derate Completed During Year N Status OP Synchronized to Transmission Grid X Operating Month 1 Operating Year 1912 Associated with Combined Heat and Power System N Sector Name Electric Utility Sector 1 Topping or Bottoming X Energy Source 1 WAT Turbines or Hydrokinetic Buoys 0 Time from Cold Shutdown to Full Load 12H Original text OP source_record_id 3_1_Generator_Y2025.xlsx#Operable:5220
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860 ↗ Data Source 2025 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location 3_1_Generator_Y2025.xlsx#Operable:5220
Sources EV-df9ff0a2b8b69bfad52b5b6a Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba 행 SHA-256 a61700fff80bdb64917a62af28a7c823579d0c5cb20796f233eb64c7b92565ce Usage terms US government public domain
Observations for this power asset Source snapshots by date · USA · eia860m Buck Hydro / 1 Generator · Operations
Metric or condition Source value Basis, scope and stage
Detailed source fields Original source field Published value or condition Entity ID 733 Entity Name Appalachian Power Co Plant ID 3772 Plant Name Buck Hydro Google Map Map Bing Map Map Plant State VA County Carroll Balancing Authority Code PJM Sector Electric Utility Generator ID 1 Nameplate Capacity (MW) 2.8 Net Summer Capacity (MW) 3 Net Winter Capacity (MW) 5.3 Technology Conventional Hydroelectric Energy Source Code WAT Prime Mover Code HY Operating Month 1 Operating Year 1912 Status (OP) Operating Latitude 36.808229 Longitude -80.93871 Original text (OP) Operating source_record_id Operating:5225
Parent facility or plant record
No separate metric summary is available. Consult the detailed source fields.
Sources, reference dates and retrieval dates 1items eia860m ↗ Data Source 2026-08 · Retrieved 2026-10-05
Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.
Source location Operating:5225
Sources EV-67b39c47a77961a82bc4b706 Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c 행 SHA-256 2c1eb65a61776ec250475888f0b51fe873a18c37870e38db460ea129f42d1c00 Usage terms US government public domain