POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Newman / CT2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)85 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-7328a2f0acd1b8aba5a225a6
Net Summer Capacity (MW)67 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-7328a2f0acd1b8aba5a225a6
Net Winter Capacity (MW)71 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-7328a2f0acd1b8aba5a225a6
Detailed source fields
Original source fieldPublished value or condition
Entity ID5701
Entity NameEl Paso Electric Co
Plant ID3456
Plant NameNewman
Google MapMap
Bing MapMap
Plant StateTX
CountyEl Paso
Balancing Authority CodeEPE
SectorElectric Utility
Generator IDCT2
Unit Code4CC
Nameplate Capacity (MW)85
Net Summer Capacity (MW)67
Net Winter Capacity (MW)71
TechnologyNatural Gas Fired Combined Cycle
Energy Source CodeNG
Prime Mover CodeCT
Operating Month8
Operating Year1975
Planned Retirement Month12
Planned Retirement Year2031
Status(OP) Operating
Latitude31.983587
Longitude-106.4318
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:4960

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:4955

Sources EV-e5970bd196651982cc98597e
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 54e47e4ce273fa8446a946c21f730a59b3f39b9bddf616a71004d4a979778da0

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:4960

Sources EV-7328a2f0acd1b8aba5a225a6
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 1b518c5d926e12301ee6a03a34a3d46e3b8f42ed72b865cd7abd91f03ef10ec6

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Newman / CT2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID5701
Entity NameEl Paso Electric Co
Plant ID3456
Plant NameNewman
Google MapMap
Bing MapMap
Plant StateTX
CountyEl Paso
Balancing Authority CodeEPE
SectorElectric Utility
Generator IDCT2
Unit Code4CC
Nameplate Capacity (MW)85
Net Summer Capacity (MW)67
Net Winter Capacity (MW)71
TechnologyNatural Gas Fired Combined Cycle
Energy Source CodeNG
Prime Mover CodeCT
Operating Month8
Operating Year1975
Planned Retirement Month12
Planned Retirement Year2031
Status(OP) Operating
Latitude31.983587
Longitude-106.4318
Original text(OP) Operating
source_record_idOperating:4960

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:4960

Sources EV-7328a2f0acd1b8aba5a225a6
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 1b518c5d926e12301ee6a03a34a3d46e3b8f42ed72b865cd7abd91f03ef10ec6

Usage terms US government public domain

Source snapshots by date · USA · eia860

Newman / CT2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID5701
Utility NameEl Paso Electric Co
Plant Code3456
Plant NameNewman
StateTX
CountyEl Paso
Generator IDCT2
TechnologyNatural Gas Fired Combined Cycle
Prime MoverCT
Unit Code4CC
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?N
Nameplate Capacity (MW)85
Nameplate Power Factor0.9
Summer Capacity (MW)67
Winter Capacity (MW)71
Minimum Load (MW)29
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month8
Operating Year1975
Planned Retirement Month12
Planned Retirement Year2031
Associated with Combined Heat and Power SystemN
Sector NameElectric Utility
Sector1
Topping or BottomingX
Energy Source 1NG
Solid Fuel Gasification System?N
Time from Cold Shutdown to Full Load12H
Multiple Fuels?N
Cofire Fuels?N
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:4955

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:4955

Sources EV-e5970bd196651982cc98597e
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 54e47e4ce273fa8446a946c21f730a59b3f39b9bddf616a71004d4a979778da0

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel