POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Thompson Falls / TF6

Generator · Out of service

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)7 MWOriginal source column definition · Generator · (OS) Out of service and NOT expected to return to service in next calendar year
As-of date 2026-08
Sources EV-9afa2bf503c4ba4bb2a44a68
Net Summer Capacity (MW)6.5 MWOriginal source column definition · Generator · (OS) Out of service and NOT expected to return to service in next calendar year
As-of date 2026-08
Sources EV-9afa2bf503c4ba4bb2a44a68
Net Winter Capacity (MW)6.5 MWOriginal source column definition · Generator · (OS) Out of service and NOT expected to return to service in next calendar year
As-of date 2026-08
Sources EV-9afa2bf503c4ba4bb2a44a68
Planned Uprate of Summer Capacity (MW)1.5 MWOriginal source column definition · Generator · (OS) Out of service and NOT expected to return to service in next calendar year
As-of date 2026-08
Sources EV-9afa2bf503c4ba4bb2a44a68
Detailed source fields
Original source fieldPublished value or condition
Entity ID13902
Entity NameNorthWestern Energy (MT Hydro)
Plant ID2195
Plant NameThompson Falls
Google MapMap
Bing MapMap
Plant StateMT
CountySanders
Balancing Authority CodeNWMT
SectorElectric Utility
Generator IDTF6
Nameplate Capacity (MW)7
Net Summer Capacity (MW)6.5
Net Winter Capacity (MW)6.5
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month7
Operating Year1915
Status(OS) Out of service and NOT expected to return to service in next calendar year
Planned Uprate Year2027
Planned Uprate Month2
Planned Uprate of Summer Capacity (MW)1.5
Latitude47.593155
Longitude-115.3582
Original text(OS) Out of service and NOT expected to return to service in next calendar year
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:3355

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:3349

Sources EV-619380ce37329be0562e8c8c
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 39850c4dd7d20dedfaa47fa639afe335f086939b0731021032337fdcba9445fe

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:3355

Sources EV-9afa2bf503c4ba4bb2a44a68
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 a29df974b7971f9386a3fc181f318fcb8982f5d7158d117eec984e8d379ac96e

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Thompson Falls / TF6

Generator · Out of service

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID13902
Entity NameNorthWestern Energy (MT Hydro)
Plant ID2195
Plant NameThompson Falls
Google MapMap
Bing MapMap
Plant StateMT
CountySanders
Balancing Authority CodeNWMT
SectorElectric Utility
Generator IDTF6
Nameplate Capacity (MW)7
Net Summer Capacity (MW)6.5
Net Winter Capacity (MW)6.5
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month7
Operating Year1915
Status(OS) Out of service and NOT expected to return to service in next calendar year
Planned Uprate Year2027
Planned Uprate Month2
Planned Uprate of Summer Capacity (MW)1.5
Latitude47.593155
Longitude-115.3582
Original text(OS) Out of service and NOT expected to return to service in next calendar year
source_record_idOperating:3355

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:3355

Sources EV-9afa2bf503c4ba4bb2a44a68
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 a29df974b7971f9386a3fc181f318fcb8982f5d7158d117eec984e8d379ac96e

Usage terms US government public domain

Source snapshots by date · USA · eia860

Thompson Falls / TF6

Generator · Out of service

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID13902
Utility NameNorthWestern Energy (MT Hydro)
Plant Code2195
Plant NameThompson Falls
StateMT
CountySanders
Generator IDTF6
TechnologyConventional Hydroelectric
Prime MoverHY
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
RTO/ISO LMP Node DesignationNA
RTO/ISO Location Designation for Reporting Wholesale Sales Data to FERCNA
Nameplate Capacity (MW)7
Nameplate Power Factor0.8
Summer Capacity (MW)6.5
Winter Capacity (MW)6.5
Minimum Load (MW)1
Uprate or Derate Completed During YearN
StatusOS
Synchronized to Transmission GridX
Operating Month7
Operating Year1915
Associated with Combined Heat and Power SystemN
Sector NameElectric Utility
Sector1
Topping or BottomingX
Energy Source 1WAT
Solid Fuel Gasification System?N
Carbon Capture Technology?N
Time from Cold Shutdown to Full Load10M
Planned Net Summer Capacity Uprate (MW)1.5
Planned Net Winter Capacity Uprate (MW)1.5
Planned Uprate Month2
Planned Uprate Year2027
Multiple Fuels?N
Original textOS
source_record_id3_1_Generator_Y2025.xlsx#Operable:3349

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:3349

Sources EV-619380ce37329be0562e8c8c
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 39850c4dd7d20dedfaa47fa639afe335f086939b0731021032337fdcba9445fe

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel