Power assets and projects · USA · eia860m
Cambridge CT Hybrid / BA1
Generator · Plan
Metric or condition
Source value
Basis, scope and stage
Nameplate Capacity (MW)
1 MW
Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-f878b3b0e28d1e74861d9b97
Net Summer Capacity (MW)
0.8 MW
Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-f878b3b0e28d1e74861d9b97
Net Winter Capacity (MW)
0.8 MW
Original source column definition · Generator · (U) Under construction, less than or equal to 50 percent complete As-of date 2026-08 Sources EV-f878b3b0e28d1e74861d9b97
Detailed source fields
Original source field
Published value or condition
Entity ID
7570
Entity Name
Great River Energy
Plant ID
2038
Plant Name
Cambridge CT Hybrid
Google Map
Map
Bing Map
Map
Plant State
MN
County
Isanti
Balancing Authority Code
MISO
Sector
Electric Utility
Generator ID
BA1
Nameplate Capacity (MW)
1
Net Summer Capacity (MW)
0.8
Net Winter Capacity (MW)
0.8
Technology
Batteries
Energy Source Code
MWH
Prime Mover Code
BA
Planned Operation Month
12
Planned Operation Year
2027
Status
(U) Under construction, less than or equal to 50 percent complete
Latitude
45.601
Longitude
-93.2081
Original text
(U) Under construction, less than or equal to 50 percent complete