POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Blakely Mountain / 2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)37.5 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-10201ab77faabefb380b35a0
Net Summer Capacity (MW)37.5 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-10201ab77faabefb380b35a0
Net Winter Capacity (MW)37.5 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-10201ab77faabefb380b35a0
Detailed source fields
Original source fieldPublished value or condition
Entity ID19406
Entity NameUSCE -Vickburg District
Plant ID197
Plant NameBlakely Mountain
Google MapMap
Bing MapMap
Plant StateAR
CountyGarland
Balancing Authority CodeMISO
SectorElectric Utility
Generator ID2
Nameplate Capacity (MW)37.5
Net Summer Capacity (MW)37.5
Net Winter Capacity (MW)37.5
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month10
Operating Year1955
Status(OP) Operating
Latitude34.570984
Longitude-93.19443
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:390

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:389

Sources EV-1d7b1055b1ea98bcfe6d8b09
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 8508e2974a6235c3488de51a6d30506a8be9147b646b43ffaaceb8b42879275a

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:390

Sources EV-10201ab77faabefb380b35a0
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 8d07c9f625ac435a06f2249698bee73fe49753411a2407c9cabfbf7ffd2240ce

Usage terms US government public domain

Source snapshots by date · USA · eia860

Blakely Mountain / 2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID19406
Utility NameUSCE -Vickburg District
Plant Code197
Plant NameBlakely Mountain
StateAR
CountyGarland
Generator ID2
TechnologyConventional Hydroelectric
Prime MoverHY
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)37.5
Nameplate Power Factor0.9
Summer Capacity (MW)37.5
Winter Capacity (MW)37.5
Minimum Load (MW)20
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month10
Operating Year1955
Associated with Combined Heat and Power SystemN
Sector NameElectric Utility
Sector1
Topping or BottomingX
Energy Source 1WAT
Time from Cold Shutdown to Full Load10M
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:389

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:389

Sources EV-1d7b1055b1ea98bcfe6d8b09
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 8508e2974a6235c3488de51a6d30506a8be9147b646b43ffaaceb8b42879275a

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Blakely Mountain / 2

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID19406
Entity NameUSCE -Vickburg District
Plant ID197
Plant NameBlakely Mountain
Google MapMap
Bing MapMap
Plant StateAR
CountyGarland
Balancing Authority CodeMISO
SectorElectric Utility
Generator ID2
Nameplate Capacity (MW)37.5
Net Summer Capacity (MW)37.5
Net Winter Capacity (MW)37.5
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month10
Operating Year1955
Status(OP) Operating
Latitude34.570984
Longitude-93.19443
Original text(OP) Operating
source_record_idOperating:390

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:390

Sources EV-10201ab77faabefb380b35a0
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 8d07c9f625ac435a06f2249698bee73fe49753411a2407c9cabfbf7ffd2240ce

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel