Power assets and projects · USA · eia860m

Oliver / 3

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)2.7 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-215f72d6eb7673639030f772
Net Summer Capacity (MW)3 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-215f72d6eb7673639030f772
Net Winter Capacity (MW)3 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-215f72d6eb7673639030f772
Detailed source fields
Original source fieldPublished value or condition
Entity ID5109
Entity NameDTE Electric Company
Plant ID1735
Plant NameOliver
Google MapMap
Bing MapMap
Plant StateMI
CountyHuron
Balancing Authority CodeMISO
SectorElectric Utility
Generator ID3
Nameplate Capacity (MW)2.7
Net Summer Capacity (MW)3
Net Winter Capacity (MW)3
TechnologyPetroleum Liquids
Energy Source CodeDFO
Prime Mover CodeIC
Operating Month1
Operating Year1970
Status(OP) Operating
Latitude43.8264
Longitude-83.2383
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:2622

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:2613

Sources EV-5b5915c9729be0274abdecff
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 061d0dd03dee7186d8ced6cd14dac1789e7cbc24e0b62f3b8e8106eaa9718396

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:2622

Sources EV-215f72d6eb7673639030f772
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 95ee49f8a492e5286707f2a7b15ee54ee06c550c2c9acc9b3e20ec222135fd7e

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Oliver / 3

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID5109
Entity NameDTE Electric Company
Plant ID1735
Plant NameOliver
Google MapMap
Bing MapMap
Plant StateMI
CountyHuron
Balancing Authority CodeMISO
SectorElectric Utility
Generator ID3
Nameplate Capacity (MW)2.7
Net Summer Capacity (MW)3
Net Winter Capacity (MW)3
TechnologyPetroleum Liquids
Energy Source CodeDFO
Prime Mover CodeIC
Operating Month1
Operating Year1970
Status(OP) Operating
Latitude43.8264
Longitude-83.2383
Original text(OP) Operating
source_record_idOperating:2622

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:2622

Sources EV-215f72d6eb7673639030f772
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 95ee49f8a492e5286707f2a7b15ee54ee06c550c2c9acc9b3e20ec222135fd7e

Usage terms US government public domain

Source snapshots by date · USA · eia860

Oliver / 3

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID5109
Utility NameDTE Electric Company
Plant Code1735
Plant NameOliver
StateMI
CountyHuron
Generator ID3
TechnologyPetroleum Liquids
Prime MoverIC
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)2.7
Nameplate Power Factor0.8
Summer Capacity (MW)3
Winter Capacity (MW)3
Minimum Load (MW)0.6
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month1
Operating Year1970
Associated with Combined Heat and Power SystemN
Sector NameElectric Utility
Sector1
Topping or BottomingX
Energy Source 1DFO
Solid Fuel Gasification System?N
Carbon Capture Technology?N
Time from Cold Shutdown to Full Load10M
Multiple Fuels?N
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:2613

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:2613

Sources EV-5b5915c9729be0274abdecff
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 061d0dd03dee7186d8ced6cd14dac1789e7cbc24e0b62f3b8e8106eaa9718396

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel