POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Conners Creek / 2

Generator · Retired

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)2.7 MWOriginal source column definition · Generator · Retired
As-of date 2026-08
Sources EV-3dac1e3bd956d8e6718bcf94
Net Summer Capacity (MW)2.3 MWOriginal source column definition · Generator · Retired
As-of date 2026-08
Sources EV-3dac1e3bd956d8e6718bcf94
Net Winter Capacity (MW)2.8 MWOriginal source column definition · Generator · Retired
As-of date 2026-08
Sources EV-3dac1e3bd956d8e6718bcf94
Detailed source fields
Original source fieldPublished value or condition
Entity ID5109
Entity NameDTE Electric Company
Plant ID1726
Plant NameConners Creek
Google MapMap
Bing MapMap
Plant StateMI
CountyWayne
Balancing Authority CodeMISO
SectorElectric Utility
Generator ID2
Nameplate Capacity (MW)2.7
Net Summer Capacity (MW)2.3
Net Winter Capacity (MW)2.8
TechnologyPetroleum Liquids
Energy Source CodeDFO
Prime Mover CodeIC
Operating Month2
Operating Year1971
Retirement Month3
Retirement Year2013
Latitude42.3592
Longitude-82.9597
Original textRetired
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idRetired:4322

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Retired and Canceled:1225

Sources EV-44c444243a8d52a847882495
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 59d5208f3fa28cc6ccbfbafecd7d37444ad45d4e2a63b557806a99ffcb620a82

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Retired:4322

Sources EV-3dac1e3bd956d8e6718bcf94
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 f642e344547dbdfe9684bf3378f5eb3453cae820f366f821fdf774dcbaf3edf3

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Conners Creek / 2

Generator · Retired

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID5109
Entity NameDTE Electric Company
Plant ID1726
Plant NameConners Creek
Google MapMap
Bing MapMap
Plant StateMI
CountyWayne
Balancing Authority CodeMISO
SectorElectric Utility
Generator ID2
Nameplate Capacity (MW)2.7
Net Summer Capacity (MW)2.3
Net Winter Capacity (MW)2.8
TechnologyPetroleum Liquids
Energy Source CodeDFO
Prime Mover CodeIC
Operating Month2
Operating Year1971
Retirement Month3
Retirement Year2013
Latitude42.3592
Longitude-82.9597
Original textRetired
source_record_idRetired:4322

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Retired:4322

Sources EV-3dac1e3bd956d8e6718bcf94
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 f642e344547dbdfe9684bf3378f5eb3453cae820f366f821fdf774dcbaf3edf3

Usage terms US government public domain

Source snapshots by date · USA · eia860

Conners Creek / 2

Generator · Retired

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID5109
Utility NameDTE Electric Company
Plant Code1726
Plant NameConners Creek
StateMI
CountyWayne
Generator ID2
TechnologyPetroleum Liquids
Prime MoverIC
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)2.7
Summer Capacity (MW)2.3
Winter Capacity (MW)2.8
Uprate or Derate Completed During YearN
StatusRE
Synchronized to Transmission GridX
Operating Month2
Operating Year1971
Retirement Month3
Retirement Year2013
Associated with Combined Heat and Power SystemN
Sector NameElectric Utility
Sector1
Topping or BottomingX
Energy Source 1DFO
Solid Fuel Gasification System?N
Carbon Capture Technology?N
Original textRE
source_record_id3_1_Generator_Y2025.xlsx#Retired and Canceled:1225

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Retired and Canceled:1225

Sources EV-44c444243a8d52a847882495
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 59d5208f3fa28cc6ccbfbafecd7d37444ad45d4e2a63b557806a99ffcb620a82

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel