POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Gulf Island / GI3

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)6.4 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-25caf80df80868651f3f135c
Net Summer Capacity (MW)7.9 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-25caf80df80868651f3f135c
Net Winter Capacity (MW)7.9 MWOriginal source column definition · Generator · (OP) Operating
As-of date 2026-08
Sources EV-25caf80df80868651f3f135c
Detailed source fields
Original source fieldPublished value or condition
Entity ID39006
Entity NameBrookfield White Pine Hydro LLC
Plant ID1491
Plant NameGulf Island
Google MapMap
Bing MapMap
Plant StateME
CountyAndroscoggin
Balancing Authority CodeISNE
SectorIPP Non-CHP
Generator IDGI3
Nameplate Capacity (MW)6.4
Net Summer Capacity (MW)7.9
Net Winter Capacity (MW)7.9
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month1
Operating Year1926
Status(OP) Operating
Latitude44.152854
Longitude-70.20938
Original text(OP) Operating
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idOperating:2387

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:2377

Sources EV-dc425070efa686e89041c4c7
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 e8a561c1b05cf9d3040841e6af9e42809fb8ce832a5000534fbf148a5d738896

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:2387

Sources EV-25caf80df80868651f3f135c
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 d605a576640382c57c1875c6e364aefd5dc5843b9931067e64cd2cdd2e0d7076

Usage terms US government public domain

Source snapshots by date · USA · eia860

Gulf Island / GI3

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID39006
Utility NameBrookfield White Pine Hydro LLC
Plant Code1491
Plant NameGulf Island
StateME
CountyAndroscoggin
Generator IDGI3
TechnologyConventional Hydroelectric
Prime MoverHY
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
Nameplate Capacity (MW)6.4
Nameplate Power Factor0.8
Summer Capacity (MW)7.9
Winter Capacity (MW)7.9
Minimum Load (MW)0.5
Uprate or Derate Completed During YearN
StatusOP
Synchronized to Transmission GridX
Operating Month1
Operating Year1926
Associated with Combined Heat and Power SystemN
Sector NameIPP Non-CHP
Sector2
Topping or BottomingX
Energy Source 1WAT
Turbines or Hydrokinetic Buoys0
Time from Cold Shutdown to Full Load10M
Original textOP
source_record_id3_1_Generator_Y2025.xlsx#Operable:2377

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Operable:2377

Sources EV-dc425070efa686e89041c4c7
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 e8a561c1b05cf9d3040841e6af9e42809fb8ce832a5000534fbf148a5d738896

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Gulf Island / GI3

Generator · Operations

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID39006
Entity NameBrookfield White Pine Hydro LLC
Plant ID1491
Plant NameGulf Island
Google MapMap
Bing MapMap
Plant StateME
CountyAndroscoggin
Balancing Authority CodeISNE
SectorIPP Non-CHP
Generator IDGI3
Nameplate Capacity (MW)6.4
Net Summer Capacity (MW)7.9
Net Winter Capacity (MW)7.9
TechnologyConventional Hydroelectric
Energy Source CodeWAT
Prime Mover CodeHY
Operating Month1
Operating Year1926
Status(OP) Operating
Latitude44.152854
Longitude-70.20938
Original text(OP) Operating
source_record_idOperating:2387

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Operating:2387

Sources EV-25caf80df80868651f3f135c
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 d605a576640382c57c1875c6e364aefd5dc5843b9931067e64cd2cdd2e0d7076

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel