POWER & FACILITY EVIDENCE

Power and Facility Evidence Database

Review power assets, contract observations, facility specifications and relationships from public sources.

This partial collection preserves source-level observations. Generation and registered connection capacity are distinct from spare supply capacity for data centers. Planned dates and contract announcements do not confirm energization or supply commencement.

Current filters 3items · current page 1–3 · Source records, not unique facilities.

Power assets and projects · USA · eia860m

Taconite Harbor Energy Center / GEN2

Generator · Retired

Metric or conditionSource valueBasis, scope and stage
Nameplate Capacity (MW)84 MWOriginal source column definition · Generator · Retired
As-of date 2026-08
Sources EV-bdba6b16befc5b36fd0d1c2e
Net Summer Capacity (MW)75.9 MWOriginal source column definition · Generator · Retired
As-of date 2026-08
Sources EV-bdba6b16befc5b36fd0d1c2e
Net Winter Capacity (MW)75.9 MWOriginal source column definition · Generator · Retired
As-of date 2026-08
Sources EV-bdba6b16befc5b36fd0d1c2e
Detailed source fields
Original source fieldPublished value or condition
Entity ID12647
Entity NameALLETE, Inc.
Plant ID10075
Plant NameTaconite Harbor Energy Center
Google MapMap
Bing MapMap
Plant StateMN
CountyCook
Balancing Authority CodeMISO
SectorElectric Utility
Generator IDGEN2
Nameplate Capacity (MW)84
Net Summer Capacity (MW)75.9
Net Winter Capacity (MW)75.9
TechnologyConventional Steam Coal
Energy Source CodeSUB
Prime Mover CodeST
Operating Month1
Operating Year1957
Retirement Month3
Retirement Year2023
Latitude47.5314
Longitude-90.9114
Original textRetired
Coordinate accuracysource_precision_not_independently_surveyed
source_record_idRetired:955

Parent facility or plant record

Coordinates locate the plant, including when this record describes one generator.

Location: Plant location · not an individual generator location

Sources, reference dates and retrieval dates 2items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Retired and Canceled:3181

Sources EV-dd691149536c7d0e99459d2d
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 012534c243f5f09590897e2242e76208faa32a56806a812b2479aa1887b42cfe

Usage terms US government public domain

eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Retired:955

Sources EV-bdba6b16befc5b36fd0d1c2e
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 c3bd48158b6587740b753924f95e40976ac5a3e64e6492766fcca7807f675dba

Usage terms US government public domain

Source snapshots by date · USA · eia860

Taconite Harbor Energy Center / GEN2

Generator · Retired

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Utility ID12647
Utility NameALLETE, Inc.
Plant Code10075
Plant NameTaconite Harbor Energy Center
StateMN
CountyCook
Generator IDGEN2
TechnologyConventional Steam Coal
Prime MoverST
OwnershipS
Duct BurnersX
Can Bypass Heat Recovery Steam Generator?X
RTO/ISO LMP Node DesignationMP.TACHB2
RTO/ISO Location Designation for Reporting Wholesale Sales Data to FERCMP.TACHB2
Nameplate Capacity (MW)84
Nameplate Power Factor0.9
Summer Capacity (MW)75.9
Winter Capacity (MW)75.9
Minimum Load (MW)32
Uprate or Derate Completed During YearN
StatusRE
Synchronized to Transmission GridX
Operating Month1
Operating Year1957
Retirement Month3
Retirement Year2023
Associated with Combined Heat and Power SystemN
Sector NameElectric Utility
Sector1
Topping or BottomingX
Energy Source 1SUB
Energy Source 2DFO
Energy Source 3BIT
Startup Source 1DFO
Solid Fuel Gasification System?N
Carbon Capture Technology?N
Time from Cold Shutdown to Full LoadOVER
Pulverized Coal Technology?Y
Subcritical Technology?Y
Multiple Fuels?Y
Original textRE
source_record_id3_1_Generator_Y2025.xlsx#Retired and Canceled:3181

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860 ↗

Data Source 2025 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location 3_1_Generator_Y2025.xlsx#Retired and Canceled:3181

Sources EV-dd691149536c7d0e99459d2d
Evidence SHA-256 2b27929d26cc1da9ad6a530da1cac6718cd8496098ee560c4d47cfffd96d08ba
행 SHA-256 012534c243f5f09590897e2242e76208faa32a56806a812b2479aa1887b42cfe

Usage terms US government public domain

Source snapshots by date · USA · eia860m

Taconite Harbor Energy Center / GEN2

Generator · Retired

Metric or conditionSource valueBasis, scope and stage
Detailed source fields
Original source fieldPublished value or condition
Entity ID12647
Entity NameALLETE, Inc.
Plant ID10075
Plant NameTaconite Harbor Energy Center
Google MapMap
Bing MapMap
Plant StateMN
CountyCook
Balancing Authority CodeMISO
SectorElectric Utility
Generator IDGEN2
Nameplate Capacity (MW)84
Net Summer Capacity (MW)75.9
Net Winter Capacity (MW)75.9
TechnologyConventional Steam Coal
Energy Source CodeSUB
Prime Mover CodeST
Operating Month1
Operating Year1957
Retirement Month3
Retirement Year2023
Latitude47.5314
Longitude-90.9114
Original textRetired
source_record_idRetired:955

Parent facility or plant record

No separate metric summary is available. Consult the detailed source fields.

Sources, reference dates and retrieval dates 1items
eia860m ↗

Data Source 2026-08 · Retrieved 2026-10-05

Source: U.S. Energy Information Administration (EIA), 2025 final / August 2026 preliminary.

Source location Retired:955

Sources EV-bdba6b16befc5b36fd0d1c2e
Evidence SHA-256 b4b70abb4c217e8e2658c3bde7608a3d530e86a81279ccc572ced82a200e9f1c
행 SHA-256 c3bd48158b6587740b753924f95e40976ac5a3e64e6492766fcca7807f675dba

Usage terms US government public domain

AI-DC KOREA MEMBER

Log In

Sign in to continue on this page.

G Continue with GoogleK Continue with Kakao

Choose the Google or Kakao account you registered with.

Start a consultation · Choose a channel